Flow, Heat‐Transfer, and Mixing Behaviors of Scrap Steel in a Refining Ladle with Bottom Blowing

The flow, heat‐transfer, and mixing behaviors of steel scraps with different amounts, positions, and sizes added from the top of the bottom‐blown 300 t ladle are numerically investigated and compared through a coupled model. In the results, it is shown that it takes 59 s to mix the temperature of molten steel after adding scrap steel at the position of x = 0 mm, y = 553.5 mm, and z = 3375 mm. The further the addition position is from the axial position of the permeable brick, the shorter the mixing time of the speed and temperature of molten steel. For the scrap amount of 0.5, 1.5, and 2.5 t, the mixing time of molten steel temperature is 44, 78, and 47 s, correspondingly, which exhibits a pattern of initial increase followed by decrease, with an ≈8 K decline in molten steel temperature for every additional 1.0 t of scrap. When considering the scrap size of 10, 30, and 50 mm, the average temperature mixing time of molten steel is 44, 61, and 45 s, respectively. In this research, theoretical guidance can be can be provided for the addition of scrap in ladle during practical production processes.

Authors

Institutions

Publication Details

Journal
steel research international
Published
2024-10-31
DOI
https://doi.org/10.1002/srin.202400596
Citations
3
Primary Topic
Metallurgical Processes and Thermodynamics
Type
article
Field-Weighted Citation Impact
0.64

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Flow, Heat‐Transfer, and Mixing Behaviors of Scrap Steel in a Refining Ladle with Bottom Blowing

Hongwei Ni, Qing Fang, Yuxiang Li, Hua Zhang et al.
3 citations
steel research international
Metallurgical Processes and Thermodynamics
0.64
article

Flow, Heat‐Transfer, and Mixing Behaviors of Scrap Steel in a Refining Ladle with Bottom Blowing

Hongwei Ni, Qing Fang, Yuxiang Li, Hua Zhang, Lichao Zhang, Xueting Li, Jianhao Wang
article en
3 citations

Abstract

The flow, heat‐transfer, and mixing behaviors of steel scraps with different amounts, positions, and sizes added from the top of the bottom‐blown 300 t ladle are numerically investigated and compared through a coupled model. In the results, it is shown that it takes 59 s to mix the temperature of molten steel after adding scrap steel at the position of x = 0 mm, y = 553.5 mm, and z = 3375 mm. The further the addition position is from the axial position of the permeable brick, the shorter the mixing time of the speed and temperature of molten steel. For the scrap amount of 0.5, 1.5, and 2.5 t, the mixing time of molten steel temperature is 44, 78, and 47 s, correspondingly, which exhibits a pattern of initial increase followed by decrease, with an ≈8 K decline in molten steel temperature for every additional 1.0 t of scrap. When considering the scrap size of 10, 30, and 50 mm, the average temperature mixing time of molten steel is 44, 61, and 45 s, respectively. In this research, theoretical guidance can be can be provided for the addition of scrap in ladle during practical production processes.

steel research internationalVol. 96(3)
The University of Queensland (AU), Wuhan University of Science and Technology (CN)
National Natural Science Foundation of China, China Scholarship Council, Wuhan University, Wuhan University of Science and Technology
Openalex Percentile: Top 35%
Metallurgical Processes and Thermodynamics
0.64
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.