Empirical Study on Delays in Highway Projects: A Comparative Analysis of Small and Large Projects

Delays in National Highway projects, regardless of their geographical location, have exerted a substantial impact on project performance and yielded unfavourable economic consequences. The majority of these projects in India are implemented by Public-Private Partnerships (PPPs), which use a wide range of contract types, including traditional ones such as item rate contracts and bills of quantity, in addition to more modern alternatives such as build operate transfer, engineering procurement and transfer, and recently developed hybrid models. This study examines and compares the reasons of critical delays in national highway projects in Himachal Pradesh with project characteristics. This mixed-methods study gathered comprehensive data from project participants using qualitative analysis and a survey questionnaire. Interviews and document analysis identified delay factors, which were then assessed through a structured questionnaire distributed to a representative sample of project participants. The findings highlight critical delay factors in National Highway projects in Himachal Pradesh and offer insights into the unique challenges faced by large PPP projects and small traditional projects. Despite the small sample size of 134 survey responses, the findings are significant but may have limited applicability to other infrastructure projects due to socio-economic and geographic variations. This suggests a research gap indicating that further analysis is needed to understand the challenges in EPC and PPPs for large hilly road projects, along with a focused study on organizational culture to assess highway project performance. This study contributes empirical data to the literature about the steep National Highway projects in Himachal Pradesh. Policymakers, project specialists, and stakeholders may ascertain the reasons of delays and formulate targeted actions to enhance project efficiency.

Authors

Institutions

Publication Details

Journal
Shanlax International Journal of Management
Published
2024-10-01
DOI
https://doi.org/10.34293/management.v12i2.7945
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Empirical Study on Delays in Highway Projects: A Comparative Analysis of Small and Large Projects

Santosh Kumari, Modish Kumar
Shanlax International Journal of Management
Construction Project Management and Performance
article

Empirical Study on Delays in Highway Projects: A Comparative Analysis of Small and Large Projects

Santosh Kumari, Modish Kumar
article en

Abstract

Delays in National Highway projects, regardless of their geographical location, have exerted a substantial impact on project performance and yielded unfavourable economic consequences. The majority of these projects in India are implemented by Public-Private Partnerships (PPPs), which use a wide range of contract types, including traditional ones such as item rate contracts and bills of quantity, in addition to more modern alternatives such as build operate transfer, engineering procurement and transfer, and recently developed hybrid models. This study examines and compares the reasons of critical delays in national highway projects in Himachal Pradesh with project characteristics. This mixed-methods study gathered comprehensive data from project participants using qualitative analysis and a survey questionnaire. Interviews and document analysis identified delay factors, which were then assessed through a structured questionnaire distributed to a representative sample of project participants. The findings highlight critical delay factors in National Highway projects in Himachal Pradesh and offer insights into the unique challenges faced by large PPP projects and small traditional projects. Despite the small sample size of 134 survey responses, the findings are significant but may have limited applicability to other infrastructure projects due to socio-economic and geographic variations. This suggests a research gap indicating that further analysis is needed to understand the challenges in EPC and PPPs for large hilly road projects, along with a focused study on organizational culture to assess highway project performance. This study contributes empirical data to the literature about the steep National Highway projects in Himachal Pradesh. Policymakers, project specialists, and stakeholders may ascertain the reasons of delays and formulate targeted actions to enhance project efficiency.

Shanlax International Journal of ManagementVol. 12(2)
Central University of Himachal Pradesh (IN), Government of Himachal Pradesh (IN), Himachal Pradesh University (IN)
Openalex Percentile: Top 77%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.