The Risk Management And Usage Of The Net Present Value-At-Risk To Evaluate Indonesian Toll Road

This study evaluates the financial feasibility and risk management of toll road infrastructure so as characteristics of toll road projects prone to risks and uncertainties. The study was conducted using case study and qualitative methods. The parameters used to determine the fair value of the project through parameters such as NPV, IRR, Payback Period, NPV at risk, and Risk Adjusted Return on Capital (RAROC) for financial and risk-based feasibility evaluation. This study also conducted a risk assessment in risk management analysis. The study provides various illustrations of possible outputs (NPV) and risk variability so that it can provide a more communicative and varied offer and recommendation, especially for investors as a consideration in making investment decisions. The results of the risk assesment process showed a low to the very high-risk level that requires different treatment. This study contributes understanding the investment in Indonesia toll road project

Authors

Institutions

Publication Details

Journal
EKOMBIS REVIEW Jurnal Ilmiah Ekonomi dan Bisnis
Published
2024-10-09
DOI
https://doi.org/10.37676/ekombis.v12i4.6419
Primary Topic
Urban Transport Systems Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The Risk Management And Usage Of The Net Present Value-At-Risk To Evaluate Indonesian Toll Road

Dewi Hanggraeni, Natasha Evelyn Saragih
EKOMBIS REVIEW Jurnal Ilmiah Ekonomi dan Bisnis
Urban Transport Systems Analysis
article

The Risk Management And Usage Of The Net Present Value-At-Risk To Evaluate Indonesian Toll Road

Dewi Hanggraeni, Natasha Evelyn Saragih
article en

Abstract

This study evaluates the financial feasibility and risk management of toll road infrastructure so as characteristics of toll road projects prone to risks and uncertainties. The study was conducted using case study and qualitative methods. The parameters used to determine the fair value of the project through parameters such as NPV, IRR, Payback Period, NPV at risk, and Risk Adjusted Return on Capital (RAROC) for financial and risk-based feasibility evaluation. This study also conducted a risk assessment in risk management analysis. The study provides various illustrations of possible outputs (NPV) and risk variability so that it can provide a more communicative and varied offer and recommendation, especially for investors as a consideration in making investment decisions. The results of the risk assesment process showed a low to the very high-risk level that requires different treatment. This study contributes understanding the investment in Indonesia toll road project

EKOMBIS REVIEW Jurnal Ilmiah Ekonomi dan BisnisVol. 12(4)
Master's College (US)
Openalex Percentile: Top 79%
Urban Transport Systems Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.