Project Management Maturity Level and PMBOK 7th Recommendations: Case Study of an IT Service Provider Company

As a provider of consulting and solutions in the ICT field, PT XYZ has the responsibility to complete projects within budget, on time, and meeting all specified scopes. However, projects from 2022-2023 have experienced delays in completion ranging from 1-6 months from the initial planning. This has resulted in the projects being considered unsuccessful due to these delays. Based on the analysis, there is a need to analyze the project management maturity level in PT XYZ's CRM division. This research aims to measure the project management maturity level and provide recommendations to improve it to the desired level. The maturity level measurement will use the Kerzner Project Management Maturity Model (KPM3). Through the measurement results, it was found that PT XYZ's CRM division has not yet passed the first level. Recommendations have been provided based on KPM3 to progress to the next level. Knowledge area-specific recommendations have also been given based on the 7th edition of PMBOK.

Authors

Institutions

Publication Details

Journal
Indonesian Journal of Computer Science
Published
2024-08-08
DOI
https://doi.org/10.33022/ijcs.v13i4.4290
Primary Topic
Big Data and Business Intelligence
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Project Management Maturity Level and PMBOK 7th Recommendations: Case Study of an IT Service Provider Company

Maria Clara Egie
Indonesian Journal of Computer Science
Big Data and Business Intelligence
article

Project Management Maturity Level and PMBOK 7th Recommendations: Case Study of an IT Service Provider Company

Maria Clara Egie
article en

Abstract

As a provider of consulting and solutions in the ICT field, PT XYZ has the responsibility to complete projects within budget, on time, and meeting all specified scopes. However, projects from 2022-2023 have experienced delays in completion ranging from 1-6 months from the initial planning. This has resulted in the projects being considered unsuccessful due to these delays. Based on the analysis, there is a need to analyze the project management maturity level in PT XYZ's CRM division. This research aims to measure the project management maturity level and provide recommendations to improve it to the desired level. The maturity level measurement will use the Kerzner Project Management Maturity Model (KPM3). Through the measurement results, it was found that PT XYZ's CRM division has not yet passed the first level. Recommendations have been provided based on KPM3 to progress to the next level. Knowledge area-specific recommendations have also been given based on the 7th edition of PMBOK.

Indonesian Journal of Computer ScienceVol. 13(4)
University of Indonesia (ID)
Openalex Percentile: Top 72%
Big Data and Business Intelligence
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.