Study on the Uneven Distribution of Breaker Circuit Current in UHVDC Sending-end Converter Station AC Field

In recent years, China's UHVDC construction, operation and maintenance technology have gradually matured. In the process of DC capacity and actual conveying power are constantly refreshing the world records, the unknown risk of DC high-power operation has also been exposed one after another. Among them, for the first time, the contradiction between precise work current demand of the switch CT and the uneven current distribution in converter station AC field caused the partial breaker circuit current exceeds the upper limit appeared. In view of the above problems, starting from main wiring connection and line power, bus resistance distribution and the interval circuit resistance, this paper study the independent and coupling situation on the uneven distribution of breaker circuit current in UHVDC sending-end converter station AC field. Based on the analysis conclusion, the Changji converter station case was analyzed, and the prevention measures and operation suggestions were put forward.

Authors

Institutions

Publication Details

Published
2024-08-08
DOI
https://doi.org/10.1109/hvdc62448.2024.10722966
Primary Topic
High-Voltage Power Transmission Systems
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Study on the Uneven Distribution of Breaker Circuit Current in UHVDC Sending-end Converter Station AC Field

Guoqi Fan, Qingxi Duan, Dongliang Nan, Yu Duan et al.
High-Voltage Power Transmission Systems
article

Study on the Uneven Distribution of Breaker Circuit Current in UHVDC Sending-end Converter Station AC Field

Guoqi Fan, Qingxi Duan, Dongliang Nan, Yu Duan, Lu Zhang, Zhen Liu
article en

Abstract

In recent years, China's UHVDC construction, operation and maintenance technology have gradually matured. In the process of DC capacity and actual conveying power are constantly refreshing the world records, the unknown risk of DC high-power operation has also been exposed one after another. Among them, for the first time, the contradiction between precise work current demand of the switch CT and the uneven current distribution in converter station AC field caused the partial breaker circuit current exceeds the upper limit appeared. In view of the above problems, starting from main wiring connection and line power, bus resistance distribution and the interval circuit resistance, this paper study the independent and coupling situation on the uneven distribution of breaker circuit current in UHVDC sending-end converter station AC field. Based on the analysis conclusion, the Changji converter station case was analyzed, and the prevention measures and operation suggestions were put forward.

Inner Mongolia Electric Power (China) (CN), Jinhua Academy of Agricultural Sciences (CN)
Affordable and clean energy
Openalex Percentile: Top 84%
High-Voltage Power Transmission Systems
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.