Evolutionary Algorithm for the Earliness - Tardiness Project Scheduling Problem

Completing too early or too late can cause damage to the project. For example, in transporting goods to the seaports, if the shipping arrives too early, it will take time and cost to stay at the dock. In the other case, shipping too late will reduce the quality of the product and break the contract. The goal of this paper is to minimize the tardiness and earliness of those projects. First, some related studies are briefly introduced, thereby showing the role and practical applications of the MS-RCPSP (Multi-Skill Resource Constrained Project Scheduling Problem) problem and the two factors of earliness and delay in scheduling problems. The roles of earliness and tardiness in scheduling problems are also described. At the same time, the new contribution of this research is also highlighted, which is the proposal for the latest problem E-RCPSP (Earliness tardiness MS-RCPSP). This problem is the first problem in the MS-RCPSP family that considers the sum of earliness and tardiness as the objective, which has never been considered in previous studies. Then, the mathematical model of the proposed E-RCPSP problem, which includes the objective function, project components and constraints is introduced. To solve the proposed problem, two approximate algorithms based on the evolutionary algorithms GA (Genetic Algorithm) and DE (Differential Evolution) are introduced. In the last section of the article, the performance of these two algorithms is verified and compared with each other through experiments conducted on the iMOPSE benchmark dataset.}\Keywords{Network Resources Management, Earliness-Tardiness cost, Resource-constrained project scheduling, Evolutionary Algorithms, Differential evolution algorithms.

Authors

Institutions

Publication Details

Journal
Journal on Information Technologies & Communications
Published
2024-09-13
DOI
https://doi.org/10.32913/mic-ict-research-vn.v2024.n3.1288
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evolutionary Algorithm for the Earliness - Tardiness Project Scheduling Problem

Hiep L. Thi
Journal on Information Technologies & Communications
Resource-Constrained Project Scheduling
article

Evolutionary Algorithm for the Earliness - Tardiness Project Scheduling Problem

Hiep L. Thi
article en

Abstract

Completing too early or too late can cause damage to the project. For example, in transporting goods to the seaports, if the shipping arrives too early, it will take time and cost to stay at the dock. In the other case, shipping too late will reduce the quality of the product and break the contract. The goal of this paper is to minimize the tardiness and earliness of those projects. First, some related studies are briefly introduced, thereby showing the role and practical applications of the MS-RCPSP (Multi-Skill Resource Constrained Project Scheduling Problem) problem and the two factors of earliness and delay in scheduling problems. The roles of earliness and tardiness in scheduling problems are also described. At the same time, the new contribution of this research is also highlighted, which is the proposal for the latest problem E-RCPSP (Earliness tardiness MS-RCPSP). This problem is the first problem in the MS-RCPSP family that considers the sum of earliness and tardiness as the objective, which has never been considered in previous studies. Then, the mathematical model of the proposed E-RCPSP problem, which includes the objective function, project components and constraints is introduced. To solve the proposed problem, two approximate algorithms based on the evolutionary algorithms GA (Genetic Algorithm) and DE (Differential Evolution) are introduced. In the last section of the article, the performance of these two algorithms is verified and compared with each other through experiments conducted on the iMOPSE benchmark dataset.}\Keywords{Network Resources Management, Earliness-Tardiness cost, Resource-constrained project scheduling, Evolutionary Algorithms, Differential evolution algorithms.

Journal on Information Technologies & Communications
Viet Tri University of Industry (VN)
Bộ Giáo dục và Ðào tạo, Đại học Quốc gia Hà Nội
Openalex Percentile: Top 77%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Evolutionary Algorithm for the Earliness - Tardiness Project Scheduling Problem — Hiep L. Thi · Journal on Information Technologies & Communications (2024) | TGRS Research Map | TGRS