Simulation Experiment Research on the Production of Large Box Girders

This paper introduces system simulation technology into large-scale beam field production and uses the simulation software Arena (14.0) to construct a simulation model of the beam field production system considering the randomness of the actual beam field production process operation time. The relationship between the production efficiency of the beam yard and the working time system was studied. In this paper, the improvement in beam-making efficiency in the existing beam field that is achieved by the commonly used reinforcement pre-binding method in the existing beam field is analyzed and calculated, and the improvements in the production efficiency in the ordinary beam field and the intelligent beam field are quantitatively calculated and compared. The results show that (1) when the working time system is increased from 8 h/d to 12 h/d, the average occupancy time of the traditional beam-making pedestal is shortened by 11.5 h when the working time is extended by 1 h per day; (2) with the extension of the working time system, the advantages of the pre-binding method of reinforcement gradually decrease; and (3) the application of intelligent technology not only improves the production efficiency of the beam yard but also makes the beam yard’s production more flexible and more resistant to risks.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2024-10-22
DOI
https://doi.org/10.3390/buildings14113338
Citations
1
Primary Topic
Manufacturing Process and Optimization
Type
article
Field-Weighted Citation Impact
0.35
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Simulation Experiment Research on the Production of Large Box Girders

Xue Yang, Yu‐Fen Huang, Qingfu Li, Ting-Jia Yang et al.
1 citations
Buildings
Manufacturing Process and Optimization
0.35
article

Simulation Experiment Research on the Production of Large Box Girders

Xue Yang, Yu‐Fen Huang, Qingfu Li, Ting-Jia Yang, Бо Лю
article en
1 citations

Abstract

This paper introduces system simulation technology into large-scale beam field production and uses the simulation software Arena (14.0) to construct a simulation model of the beam field production system considering the randomness of the actual beam field production process operation time. The relationship between the production efficiency of the beam yard and the working time system was studied. In this paper, the improvement in beam-making efficiency in the existing beam field that is achieved by the commonly used reinforcement pre-binding method in the existing beam field is analyzed and calculated, and the improvements in the production efficiency in the ordinary beam field and the intelligent beam field are quantitatively calculated and compared. The results show that (1) when the working time system is increased from 8 h/d to 12 h/d, the average occupancy time of the traditional beam-making pedestal is shortened by 11.5 h when the working time is extended by 1 h per day; (2) with the extension of the working time system, the advantages of the pre-binding method of reinforcement gradually decrease; and (3) the application of intelligent technology not only improves the production efficiency of the beam yard but also makes the beam yard’s production more flexible and more resistant to risks.

BuildingsVol. 14(11)
Zhengzhou University (CN)
Openalex Percentile: Top 35%
Manufacturing Process and Optimization
0.35
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.