Measurement and analysis of surface settlement caused by construction of quasi-rectangular shield tunnel in rich water-sand stratum

The study is based on a section of the Zhengzhou Metro Line 8 quasi-rectangular shield tunnel. Field excavation trials were conducted to analyze the surface settlement patterns caused by the construction of a large-section quasi-rectangular shield tunnel in the rich water sand layer in Zhengzhou. Based on the characteristics of the rich water sand layer, ground settlement control measures were proposed. The research findings show that the surface settlement caused by the construction of the large-section quasi-rectangular shield tunnel in the rich water sand layer exhibits a temporal curve pattern of slow settlement (Stage I: pre-arrival of the shield), rapid settlement (Stage II: shield passage, Stage III: shield tail exiting 14.4 ~ 18 m), and stable settlement (Stage IV: late settlement). In Stage I, controlling the excavation rate to maintain balance between the cutter face pressure and soil pressure is effective. In Stage II, injecting lubricating mud between the shell and the sand layer to reduce soil friction and shear slip is recommended. In Stage III, increasing the synchronous grouting volume at the shield tail and adjusting grouting pressure, as well as timely filling the shield tail construction gap, are effective methods to reduce surface settlement. The Peck formula was used to fit the transverse settlement trough on the surface, with a linear correlation coefficient R²=0.983, validating the use of the Peck formula to predict surface settlement troughs for quasi-rectangular shield tunneling in the rich water sand layer. These research findings can provide data support and reference for similar projects.

Authors

Institutions

Publication Details

Journal
Scientific Reports
Published
2024-10-18
DOI
https://doi.org/10.1038/s41598-024-74164-3
Citations
8
Primary Topic
Geotechnical Engineering and Analysis
Type
article
Field-Weighted Citation Impact
2.92

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Measurement and analysis of surface settlement caused by construction of quasi-rectangular shield tunnel in rich water-sand stratum

Yao Ding, Qinghai Xu, Shi-ju Ma, Cheng Zhi Huang et al.
8 citations
Scientific Reports
Geotechnical Engineering and Analysis
2.92
article

Measurement and analysis of surface settlement caused by construction of quasi-rectangular shield tunnel in rich water-sand stratum

Yao Ding, Qinghai Xu, Shi-ju Ma, Cheng Zhi Huang, Ming Yan, Kairong Hong
article en
8 citations

Abstract

The study is based on a section of the Zhengzhou Metro Line 8 quasi-rectangular shield tunnel. Field excavation trials were conducted to analyze the surface settlement patterns caused by the construction of a large-section quasi-rectangular shield tunnel in the rich water sand layer in Zhengzhou. Based on the characteristics of the rich water sand layer, ground settlement control measures were proposed. The research findings show that the surface settlement caused by the construction of the large-section quasi-rectangular shield tunnel in the rich water sand layer exhibits a temporal curve pattern of slow settlement (Stage I: pre-arrival of the shield), rapid settlement (Stage II: shield passage, Stage III: shield tail exiting 14.4 ~ 18 m), and stable settlement (Stage IV: late settlement). In Stage I, controlling the excavation rate to maintain balance between the cutter face pressure and soil pressure is effective. In Stage II, injecting lubricating mud between the shell and the sand layer to reduce soil friction and shear slip is recommended. In Stage III, increasing the synchronous grouting volume at the shield tail and adjusting grouting pressure, as well as timely filling the shield tail construction gap, are effective methods to reduce surface settlement. The Peck formula was used to fit the transverse settlement trough on the surface, with a linear correlation coefficient R²=0.983, validating the use of the Peck formula to predict surface settlement troughs for quasi-rectangular shield tunneling in the rich water sand layer. These research findings can provide data support and reference for similar projects.

Scientific ReportsVol. 14(1)
Henan University of Technology (CN), Shanghai Tunnel Engineering (China) (CN), China Railway Group (China) (CN)
Zhengzhou University, Education Department of Henan Province
Sustainable cities and communities
Openalex Percentile: Top 9%
Geotechnical Engineering and Analysis
2.92
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.