Cost Contingency Strategies in Building Construction: Evaluating Project Risk Influence

Contingency costs are an important part of construction to achieve successful project management. In determining contingency costs, practitioners have used a very subjective approach. This study discussed the determination of the contingency cost of high-rise buildings in six research object projects, based on the results of risk evaluation. The risk evaluation used in this paper is based on the risks in the construction phase. The method used to know the relationship between risk and contingency costs is simple linear regression with tools. The results of this study indicate that the greater the level of risk, the greater the contingency costs incurred by the project. the risk level contributed 71.6% to the contingency cost, while the rest was influenced by other factors. The equation formed is, that if the risk increases by 1 unit, the total contingency cost will increase by 0.0916 units.

Authors

Institutions

Publication Details

Journal
Jurnal Teknologi Terapan G-Tech
Published
2024-10-14
DOI
https://doi.org/10.70609/gtech.v8i4.5115
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Cost Contingency Strategies in Building Construction: Evaluating Project Risk Influence

Putri Suci Mawariza, Michella Beatrix
Jurnal Teknologi Terapan G-Tech
Construction Project Management and Performance
article

Cost Contingency Strategies in Building Construction: Evaluating Project Risk Influence

Putri Suci Mawariza, Michella Beatrix
article en

Abstract

Contingency costs are an important part of construction to achieve successful project management. In determining contingency costs, practitioners have used a very subjective approach. This study discussed the determination of the contingency cost of high-rise buildings in six research object projects, based on the results of risk evaluation. The risk evaluation used in this paper is based on the risks in the construction phase. The method used to know the relationship between risk and contingency costs is simple linear regression with tools. The results of this study indicate that the greater the level of risk, the greater the contingency costs incurred by the project. the risk level contributed 71.6% to the contingency cost, while the rest was influenced by other factors. The equation formed is, that if the risk increases by 1 unit, the total contingency cost will increase by 0.0916 units.

Jurnal Teknologi Terapan G-TechVol. 8(4)
Universitas 17 Agustus 1945 Surabaya (ID)
Sustainable cities and communities
Openalex Percentile: Top 78%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.