Risk Management of Supply Chain in Prefabricated Buildings: A Case Study of Leishenshan Hospital

Based on the research of other scholars, this article divides the prefabricated building supply chain into six stages: design and development, production procurement, warehousing and transportation, lifting construction, and facility recycling. Taking the well-known prefabricated building of Leishenshan Hospital as an example, this study analyzes the possible risks of these six stages in the prefabricated building supply chain, such as insufficient design capabilities, production efficiency, the low standardization level of molds, transportation policy constraints, insufficient protection of components during the warehousing and transportation stage, insufficient organizational capacity, inadequate supervision, and problems such as missing recycling processes. Due to the special nature of Leishenshan Hospital, which has received great attention, some risks that have been avoided due to special reasons have been proposed, and the power of management personnel has been strengthened for these risks, digitization and standardization of molds, and strengthen on-site management level. From this study, construction, component production, and design enterprises can learn from measures such as increasing awareness of component recycling.

Authors

Institutions

Publication Details

Journal
Advances in Economics Management and Political Sciences
Published
2024-10-12
DOI
https://doi.org/10.54254/2754-1169/109/2024bj0118
Primary Topic
Occupational Health and Safety Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Management of Supply Chain in Prefabricated Buildings: A Case Study of Leishenshan Hospital

Jia-Rong Chen
Advances in Economics Management and Political Sciences
Occupational Health and Safety Research
article

Risk Management of Supply Chain in Prefabricated Buildings: A Case Study of Leishenshan Hospital

Jia-Rong Chen
article en

Abstract

Based on the research of other scholars, this article divides the prefabricated building supply chain into six stages: design and development, production procurement, warehousing and transportation, lifting construction, and facility recycling. Taking the well-known prefabricated building of Leishenshan Hospital as an example, this study analyzes the possible risks of these six stages in the prefabricated building supply chain, such as insufficient design capabilities, production efficiency, the low standardization level of molds, transportation policy constraints, insufficient protection of components during the warehousing and transportation stage, insufficient organizational capacity, inadequate supervision, and problems such as missing recycling processes. Due to the special nature of Leishenshan Hospital, which has received great attention, some risks that have been avoided due to special reasons have been proposed, and the power of management personnel has been strengthened for these risks, digitization and standardization of molds, and strengthen on-site management level. From this study, construction, component production, and design enterprises can learn from measures such as increasing awareness of component recycling.

Advances in Economics Management and Political SciencesVol. 109(1)
China University of Geosciences (CN)
Industry, innovation and infrastructure
Openalex Percentile: Top 73%
Occupational Health and Safety Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.