A Framework for Construction-related Risks by integrating the Fuzzy Grey Comprehensive Evaluation Method (FGCE)

There are five basic phases for construction projects: planning, design, tendering, construction and maintenance. The risks of each phase have an impact on time, cost, and quality. In this paper, the tendering phase of the residential complex project was investigated as a case study, and the creation of a fuzzy and grey correlation analysis model was examined using a fuzzy theory and a grey correlation theory to dispel the professional judgment around the project phase. Creating a comparison and a reference matrix based on grey theory and/by examining factors and their impact on duration, cost, and quality separately, gives the construction investors a scientific, direct, flexible, and adaptable technique to assess project risks. The described method categorized the tendering phase risk based on the three project determinants: duration, cost, and quality. The correlation degree is greater than 0.5, hence construction project duration risk is almost nonexistent. The project investor must also investigate risk assumption, reduction, diversion, and evasion tactics to handle cost and quality risks, which are between 0.2 and 0.5. This suggests that tender phase issues do not affect project length but do affect cost and quality, requiring attention and action.

Authors

Institutions

Publication Details

Journal
Engineering Technology & Applied Science Research
Published
2024-10-09
DOI
https://doi.org/10.48084/etasr.8129
Primary Topic
Occupational Health and Safety Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Framework for Construction-related Risks by integrating the Fuzzy Grey Comprehensive Evaluation Method (FGCE)

Ahmed Mohammed Raoof Mahjoob, Rana Jabbar Kasid Jalhoom
Engineering Technology & Applied Science Research
Occupational Health and Safety Research
article

A Framework for Construction-related Risks by integrating the Fuzzy Grey Comprehensive Evaluation Method (FGCE)

Ahmed Mohammed Raoof Mahjoob, Rana Jabbar Kasid Jalhoom
article en

Abstract

There are five basic phases for construction projects: planning, design, tendering, construction and maintenance. The risks of each phase have an impact on time, cost, and quality. In this paper, the tendering phase of the residential complex project was investigated as a case study, and the creation of a fuzzy and grey correlation analysis model was examined using a fuzzy theory and a grey correlation theory to dispel the professional judgment around the project phase. Creating a comparison and a reference matrix based on grey theory and/by examining factors and their impact on duration, cost, and quality separately, gives the construction investors a scientific, direct, flexible, and adaptable technique to assess project risks. The described method categorized the tendering phase risk based on the three project determinants: duration, cost, and quality. The correlation degree is greater than 0.5, hence construction project duration risk is almost nonexistent. The project investor must also investigate risk assumption, reduction, diversion, and evasion tactics to handle cost and quality risks, which are between 0.2 and 0.5. This suggests that tender phase issues do not affect project length but do affect cost and quality, requiring attention and action.

Engineering Technology & Applied Science ResearchVol. 14(5)
University of Baghdad (IQ), University of Technology - Iraq (IQ)
Openalex Percentile: Top 74%
Occupational Health and Safety Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.