Evaluation of Factors Leading to Time Delays and Cost Overruns in Marine Construction Projects

Marine construction projects are among the most complex endeavors undertaken, as they are subject to numerous variables and constraints that make them more vulnerable to cost overruns and time delays than other project types. This study investigates the potential factors that influence time delays and cost overruns in marine construction projects. For this purpose, 43 factors that affect marine construction projects in terms of cost overrun and time delay were identified and categorized into nine main groups through a detailed literature review process, as well as interviews with experts from the marine construction industry. The relative importance of these factors and groups was quantified using the Relative Importance Index (RII) method. The ranking of factors and groups was determined according to their level of effect on time delay and cost overrun. Interestingly, the top five factors for both time delay and cost overrun, although ordered differently, were the same: inflation (e.g., material, equipment, and labor prices), fluctuation in cost (e.g., money exchange rate, taxes and burdens, and interest rates charged by bankers on loans), incompetence or inexperience of contractors (lack of experience and/or managerial skills), poor planning and management of contractor's schedule, and difficulties in project financing by the contractor. Contractor-related factors had the highest RII for time delays, followed by external-related factors with a tiny difference. However, for cost overruns, the ranking of these two groups is reversed. The findings of this study could help organizations that plan to carry out successful and sustainable marine construction projects, ultimately contributing to the development of critical maritime infrastructure.

Authors

Institutions

Publication Details

Journal
Engineering Technology & Applied Science Research
Published
2024-10-09
DOI
https://doi.org/10.48084/etasr.8116
Citations
5
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.45
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evaluation of Factors Leading to Time Delays and Cost Overruns in Marine Construction Projects

Aymen Nassar, Ahmed Elbisy
5 citations
Engineering Technology & Applied Science Research
Construction Project Management and Performance
2.45
article

Evaluation of Factors Leading to Time Delays and Cost Overruns in Marine Construction Projects

Aymen Nassar, Ahmed Elbisy
article en
5 citations

Abstract

Marine construction projects are among the most complex endeavors undertaken, as they are subject to numerous variables and constraints that make them more vulnerable to cost overruns and time delays than other project types. This study investigates the potential factors that influence time delays and cost overruns in marine construction projects. For this purpose, 43 factors that affect marine construction projects in terms of cost overrun and time delay were identified and categorized into nine main groups through a detailed literature review process, as well as interviews with experts from the marine construction industry. The relative importance of these factors and groups was quantified using the Relative Importance Index (RII) method. The ranking of factors and groups was determined according to their level of effect on time delay and cost overrun. Interestingly, the top five factors for both time delay and cost overrun, although ordered differently, were the same: inflation (e.g., material, equipment, and labor prices), fluctuation in cost (e.g., money exchange rate, taxes and burdens, and interest rates charged by bankers on loans), incompetence or inexperience of contractors (lack of experience and/or managerial skills), poor planning and management of contractor's schedule, and difficulties in project financing by the contractor. Contractor-related factors had the highest RII for time delays, followed by external-related factors with a tiny difference. However, for cost overruns, the ranking of these two groups is reversed. The findings of this study could help organizations that plan to carry out successful and sustainable marine construction projects, ultimately contributing to the development of critical maritime infrastructure.

Engineering Technology & Applied Science ResearchVol. 14(5)
German University in Cairo (EG)
Openalex Percentile: Top 10%
Construction Project Management and Performance
2.45
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Evaluation of Factors Leading to Time Delays and Cost Overruns in Marine Construction Projects — Aymen Nassar, Ahmed Elbisy · Engineering Technology & Applied Science Research (2024) | TGRS Research Map | TGRS