Implementation and performance monitoring of the treatment system to remove arsenic from dam water in a full-scale urban water treatment plant

Nowadays, health and environmental problems caused by elevated arsenic concentration in water sources have become a major concern for researchers and environmental experts. Therefore, it is necessary to study processes that significantly reduce the arsenic content in aqueous solutions, which is of great interest to environmental experts. This work aimed to evaluate the effect of the pre-oxidation/coagulation process with commercially available coagulants (FeCl 3 , Al 2 (SO 4 ) 3 ·18H 2 O, and PACl) on the efficiency of arsenic removal (with initial concentration of 73 ± 2.5 μg/L) from Talvar Dam entering the Sheikhi Jan Hamadan water treatment plant. This was demonstrated on a laboratory and operational scale at the water treatment plant under different scenarios (pre-oxidant agents, type of coagulant, solution pH, and different coagulant dosages). It should be noted that, as part of an emergency project, the possibility of arsenic removal at the Sheikhi Jan water treatment plant, which receives Talvar Dam water at a flow rate of 1800 L/s, was investigated. The priority of the researchers and city officials in the present study was to use the potential of the water treatment plant and the existing equipment so that they could remove arsenic quickly and without additional costs. This study was conducted in three stages: laboratory scale, implementation of the process in the water treatment plant, and monitoring of the treatment plant's performance, which continues to this day. The results of this project showed that the pre-oxidation/coagulation process can effectively reduce the concentration of arsenic at the inlet of the treatment plant from to less than national and international recommended values. • Arsenic concentrations above the permissible limit were detected in the Talvar Dam. • Improved removal of arsenic in the pre-oxidation/coagulation process. • FeCl 3 was an effective coagulant in a wide pH range for arsenic removal. • A combined process for arsenic removal was fully implemented in emergency conditions. • The arsenic concentration as a result of the process reached less than the 10 μg/L.

Authors

Institutions

Publication Details

Journal
Results in Engineering
Published
2024-10-09
DOI
https://doi.org/10.1016/j.rineng.2024.103087
Citations
9
Primary Topic
Arsenic contamination and mitigation
Type
article
Field-Weighted Citation Impact
2.25

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Implementation and performance monitoring of the treatment system to remove arsenic from dam water in a full-scale urban water treatment plant

Zahra Torkshavand, Reza Shokoohi, Roqiyeh Mostafaloo, Esmaeil Ghahramani et al.
9 citations
Results in Engineering
Arsenic contamination and mitigation
2.25
article

Implementation and performance monitoring of the treatment system to remove arsenic from dam water in a full-scale urban water treatment plant

Zahra Torkshavand, Reza Shokoohi, Roqiyeh Mostafaloo, Esmaeil Ghahramani, Maryam Roshani, Mohammad Khazaei, Hassan Zolghadr Nassab, Hadi Motaghipour, Amir Shabanloo
article en
9 citations

Abstract

Nowadays, health and environmental problems caused by elevated arsenic concentration in water sources have become a major concern for researchers and environmental experts. Therefore, it is necessary to study processes that significantly reduce the arsenic content in aqueous solutions, which is of great interest to environmental experts. This work aimed to evaluate the effect of the pre-oxidation/coagulation process with commercially available coagulants (FeCl 3 , Al 2 (SO 4 ) 3 ·18H 2 O, and PACl) on the efficiency of arsenic removal (with initial concentration of 73 ± 2.5 μg/L) from Talvar Dam entering the Sheikhi Jan Hamadan water treatment plant. This was demonstrated on a laboratory and operational scale at the water treatment plant under different scenarios (pre-oxidant agents, type of coagulant, solution pH, and different coagulant dosages). It should be noted that, as part of an emergency project, the possibility of arsenic removal at the Sheikhi Jan water treatment plant, which receives Talvar Dam water at a flow rate of 1800 L/s, was investigated. The priority of the researchers and city officials in the present study was to use the potential of the water treatment plant and the existing equipment so that they could remove arsenic quickly and without additional costs. This study was conducted in three stages: laboratory scale, implementation of the process in the water treatment plant, and monitoring of the treatment plant's performance, which continues to this day. The results of this project showed that the pre-oxidation/coagulation process can effectively reduce the concentration of arsenic at the inlet of the treatment plant from to less than national and international recommended values. • Arsenic concentrations above the permissible limit were detected in the Talvar Dam. • Improved removal of arsenic in the pre-oxidation/coagulation process. • FeCl 3 was an effective coagulant in a wide pH range for arsenic removal. • A combined process for arsenic removal was fully implemented in emergency conditions. • The arsenic concentration as a result of the process reached less than the 10 μg/L.

Results in EngineeringVol. 24
Hamedan University of Medical Sciences (IR), Kurdistan University of Medical Sciences (IR)
Hamadan University of Medical Sciences, Vice Chancellor for Research and Technology, Hamadan University of Medical Sciences
Clean water and sanitation
Openalex Percentile: Top 13%
Arsenic contamination and mitigation
2.25
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.