Optimization of Solar PV System Efficiency in Bangladesh

This paper presents a comprehensive review and analysis of Sarishabari Engreen Solar Plant Ltd., a 3.3 MW grid-connected solar photovoltaic (PV) system located in Sarishabari, Jamalpur, Bangladesh. The study evaluates the plant's economic and operational performance, revealing a competitive payback period of 10.1 years and a levelized cost of energy (LCOE) of 0.11 USD/kWh. These metrics highlight the plant's financial viability, largely due to the low cost of public land used for construction. However, profitability may be challenged if similar projects require significant investments in private land acquisition. Key areas for improvement identified include optimizing the tilt angle and integrating smart automation systems. Additionally, the potential for hybrid renewable energy systems combining solar and wind power is discussed. The paper also provides actionable recommendations for future renewable projects, emphasizing the importance of advanced technologies, and supportive policies. These insights aim to inform the optimization of existing solar PV systems and guide the development of future renewable energy projects in Bangladesh, contributing to the country's sustainable energy goals.

Authors

Institutions

Publication Details

Journal
Journal of Renewable Energy and Mechanics
Published
2024-09-30
DOI
https://doi.org/10.25299/rem.2024.17875
Citations
1
Primary Topic
Energy and Environment Impacts
Type
article
Field-Weighted Citation Impact
0.13
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimization of Solar PV System Efficiency in Bangladesh

Md. Shahidul Islam, Enamul Basher, Riad Mollik Babu
1 citations
Journal of Renewable Energy and Mechanics
Energy and Environment Impacts
0.13
article

Optimization of Solar PV System Efficiency in Bangladesh

Md. Shahidul Islam, Enamul Basher, Riad Mollik Babu
article en
1 citations

Abstract

This paper presents a comprehensive review and analysis of Sarishabari Engreen Solar Plant Ltd., a 3.3 MW grid-connected solar photovoltaic (PV) system located in Sarishabari, Jamalpur, Bangladesh. The study evaluates the plant's economic and operational performance, revealing a competitive payback period of 10.1 years and a levelized cost of energy (LCOE) of 0.11 USD/kWh. These metrics highlight the plant's financial viability, largely due to the low cost of public land used for construction. However, profitability may be challenged if similar projects require significant investments in private land acquisition. Key areas for improvement identified include optimizing the tilt angle and integrating smart automation systems. Additionally, the potential for hybrid renewable energy systems combining solar and wind power is discussed. The paper also provides actionable recommendations for future renewable projects, emphasizing the importance of advanced technologies, and supportive policies. These insights aim to inform the optimization of existing solar PV systems and guide the development of future renewable energy projects in Bangladesh, contributing to the country's sustainable energy goals.

Journal of Renewable Energy and MechanicsVol. 7(02)
University of Asia Pacific (BD)
Openalex Percentile: Top 60%
Energy and Environment Impacts
0.13
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.