Extension of Time and Liquidated Damage Issue in Construction Contract: Nepalese Legal Provision and Practice

The construction project in Nepal is severely facing the problems of on-time project completion. Poor planning preparation, and ad-hoc methods of fixing the project completion duration and milestones create confusion and disputes in the construction industry. In numerous construction projects, new project completion dates are fixed to complete the work. The side effects of the extension of time to complete the work are cost overrun, time overrun, disputes, etc. Public Procurement Act 2007 and Public Procurement Regulation 2007 has provisions to address this delay issue. The FIDIC condition of the contract has also similar to legal provisions as Nepalese Act and Regulations. The Supreme Court of Nepal has also made a landmark decision about the liabilities after the entitlement extension of time to accomplish the project. It is the collective effort of all stakeholders to finish the project on stipulated time.

Authors

Institutions

Publication Details

Journal
KTFT journal.
Published
2024-10-04
DOI
https://doi.org/10.3126/ktftj.v4i1.70449
Primary Topic
Insurance and Financial Risk Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Extension of Time and Liquidated Damage Issue in Construction Contract: Nepalese Legal Provision and Practice

Binod Shrestha
KTFT journal.
Insurance and Financial Risk Management
article

Extension of Time and Liquidated Damage Issue in Construction Contract: Nepalese Legal Provision and Practice

Binod Shrestha
article en

Abstract

The construction project in Nepal is severely facing the problems of on-time project completion. Poor planning preparation, and ad-hoc methods of fixing the project completion duration and milestones create confusion and disputes in the construction industry. In numerous construction projects, new project completion dates are fixed to complete the work. The side effects of the extension of time to complete the work are cost overrun, time overrun, disputes, etc. Public Procurement Act 2007 and Public Procurement Regulation 2007 has provisions to address this delay issue. The FIDIC condition of the contract has also similar to legal provisions as Nepalese Act and Regulations. The Supreme Court of Nepal has also made a landmark decision about the liabilities after the entitlement extension of time to accomplish the project. It is the collective effort of all stakeholders to finish the project on stipulated time.

KTFT journal.Vol. 4
United States Department of the Army (US)
Openalex Percentile: Top 79%
Insurance and Financial Risk Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.