Implementation of Material Control in Tugboat Ship Building Using the Lot For Lot (LFL) Method Case Study : (PT.PMP)

Material procurement in the shipping industry accounts for 2/3 of the total production cost. PT.PMP is a company that focuses on the shipbuilding industry including Ship Design, Ship Building and Ship Repair. In the implementation of material procurement, there are often delays in the delivery of materials from suppliers resulting in delayed production time. Material inventory in the warehouse is sometimes insufficient to meet production needs. In the Pre-Order system, the company must ensure the availability of prepared planning items, but the Company sometimes faces a shortage of raw materials which results in delays in the delivery of promised goods. Material Requirement Planning (MRP) is a method used to organize and plan material orders. The purpose of this study is to determine the material planning strategy using the Lot for Lot method and the Economic Order Quantity method comparison between efficient methods at PT.PMP and to determine the efficiency results of the comparison between the Lot for Lot (LFL) method, Economic Order Quantity (EOQ) and the existing method at PT.PMP. The materials analyzed are Plate and Profile in the New Building Tugboat Project. The results obtained from the inventory cost research that the Lot for Lot method is 28%, the Economic Order Quantity method results in an inventory cost of 29% and the company method that is still being applied results in a high cost of 43%. The Lot for Lot method is more efficient by 15% than the existing method applied by the company.

Authors

Institutions

Publication Details

Journal
International Journal of Marine Engineering Innovation and Research
Published
2024-09-16
DOI
https://doi.org/10.12962/j25481479.v9i3.20859
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Implementation of Material Control in Tugboat Ship Building Using the Lot For Lot (LFL) Method Case Study : (PT.PMP)

Tri Agung Kristiyono, Intan Baroroh, Ali Azhar, Eko Febrianto Tarigan et al.
1 links
International Journal of Marine Engineering Innovation and Research
Management and Optimization Techniques
article

Implementation of Material Control in Tugboat Ship Building Using the Lot For Lot (LFL) Method Case Study : (PT.PMP)

Tri Agung Kristiyono, Intan Baroroh, Ali Azhar, Eko Febrianto Tarigan, Siswo Hadi Sumantri, Dididk Hardianto
article en

Abstract

Material procurement in the shipping industry accounts for 2/3 of the total production cost. PT.PMP is a company that focuses on the shipbuilding industry including Ship Design, Ship Building and Ship Repair. In the implementation of material procurement, there are often delays in the delivery of materials from suppliers resulting in delayed production time. Material inventory in the warehouse is sometimes insufficient to meet production needs. In the Pre-Order system, the company must ensure the availability of prepared planning items, but the Company sometimes faces a shortage of raw materials which results in delays in the delivery of promised goods. Material Requirement Planning (MRP) is a method used to organize and plan material orders. The purpose of this study is to determine the material planning strategy using the Lot for Lot method and the Economic Order Quantity method comparison between efficient methods at PT.PMP and to determine the efficiency results of the comparison between the Lot for Lot (LFL) method, Economic Order Quantity (EOQ) and the existing method at PT.PMP. The materials analyzed are Plate and Profile in the New Building Tugboat Project. The results obtained from the inventory cost research that the Lot for Lot method is 28%, the Economic Order Quantity method results in an inventory cost of 29% and the company method that is still being applied results in a high cost of 43%. The Lot for Lot method is more efficient by 15% than the existing method applied by the company.

International Journal of Marine Engineering Innovation and ResearchVol. 9(3)
Universitas Hang Tuah (ID)
Openalex Percentile: Top 70%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.