An opinion survey of Delay in Road Construction in City Area and its effects

Purpose: This study aims to investigate the causes and effects of delays in road construction across various areas in Nepal. Its objective is to identify the key factors contributing to these delays and examine how they affect different stakeholders, including the general public, businesses, and the government.Method: This research used a mixed-method approach, combining a questionnaire survey with Focus Group Discussions (FGDs) to gather comprehensive data on road construction delays. Key stakeholders, particularly those impacted by road construction projects, were surveyed to collect their views on the causes of delays and the resulting consequences.Results: There is identified several major factors causing delays in road construction projects in Nepal including frequent government changes, alterations in project design, low labor productivity, inadequate planning, political interference and protection, and a shortage of resources. Conclusion: The study concludes that delays in road construction projects not only increase costs but also diminish public trust, growing public dissatisfaction. Stakeholders expressed frustration with the slow pace of construction, emphasizing its adverse effects on businesses, public health, and road safety.

Authors

Publication Details

Journal
The Lumbini Journal of Business and Economics
Published
2024-09-30
DOI
https://doi.org/10.3126/ljbe.v12i1.70319
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An opinion survey of Delay in Road Construction in City Area and its effects

Pramshu Nepal
The Lumbini Journal of Business and Economics
BIM and Construction Integration
article

An opinion survey of Delay in Road Construction in City Area and its effects

Pramshu Nepal
article en

Abstract

Purpose: This study aims to investigate the causes and effects of delays in road construction across various areas in Nepal. Its objective is to identify the key factors contributing to these delays and examine how they affect different stakeholders, including the general public, businesses, and the government.Method: This research used a mixed-method approach, combining a questionnaire survey with Focus Group Discussions (FGDs) to gather comprehensive data on road construction delays. Key stakeholders, particularly those impacted by road construction projects, were surveyed to collect their views on the causes of delays and the resulting consequences.Results: There is identified several major factors causing delays in road construction projects in Nepal including frequent government changes, alterations in project design, low labor productivity, inadequate planning, political interference and protection, and a shortage of resources. Conclusion: The study concludes that delays in road construction projects not only increase costs but also diminish public trust, growing public dissatisfaction. Stakeholders expressed frustration with the slow pace of construction, emphasizing its adverse effects on businesses, public health, and road safety.

The Lumbini Journal of Business and EconomicsVol. 12(1)
Openalex Percentile: Top 83%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.