Design Optimization of a Run-Of-River Small Hydropower Plant: A Case Study of Mabula Kapi Site

Prior to construction, small or large hydropower plants undergo feasibility studies, which involve technical, economic, financial, social, and environmental aspects. Technical studies, particularly, include various engineering disciplines. This study sought to conduct a component of technical feasibility studies, focused on design optimization of the turbine-plant capacity size for a run-of-river case study called Mabula Kapi, on Kaombe River, Serenje, Zambia. The study method used computational modelling, simulation, and optimization techniques, and used secondary data from previous site. A prefeasibility study conducted earlier had underestimated the turbine-plant capacity owing to underestimated discharge data, owing to lack of site gauging station. A less accurate discharge estimation method involving transposition from a gauged similar catchment had been used. A later feasibility-level site hydrological study found improved discharge data. Riding on the improved discharge data, this study found the following optimised plant design parameters based on plant design discharge of 6.20 m3/s: Installed capacity of 10.20 MW; Annual energy production of 42 GWh; Capacity factor of 47.1%; 3 x Pelton wheel of 272 rpm speed, 2.1 m diameter, 2-nozzles of diameter 0.16 m each, 21 buckets of 0.58m width each; and 3 x 4 MVA generators of 50Hz, 22-poles, and 11kV.

Authors

Institutions

Publication Details

Journal
Engineering and Technology Journal
Published
2024-09-09
DOI
https://doi.org/10.47191/etj/v9i09.08
Primary Topic
Cavitation Phenomena in Pumps
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Design Optimization of a Run-Of-River Small Hydropower Plant: A Case Study of Mabula Kapi Site

Dean Lameck Musukwa, Edwin Luwaya
Engineering and Technology Journal
Cavitation Phenomena in Pumps
article

Design Optimization of a Run-Of-River Small Hydropower Plant: A Case Study of Mabula Kapi Site

Dean Lameck Musukwa, Edwin Luwaya
article en

Abstract

Prior to construction, small or large hydropower plants undergo feasibility studies, which involve technical, economic, financial, social, and environmental aspects. Technical studies, particularly, include various engineering disciplines. This study sought to conduct a component of technical feasibility studies, focused on design optimization of the turbine-plant capacity size for a run-of-river case study called Mabula Kapi, on Kaombe River, Serenje, Zambia. The study method used computational modelling, simulation, and optimization techniques, and used secondary data from previous site. A prefeasibility study conducted earlier had underestimated the turbine-plant capacity owing to underestimated discharge data, owing to lack of site gauging station. A less accurate discharge estimation method involving transposition from a gauged similar catchment had been used. A later feasibility-level site hydrological study found improved discharge data. Riding on the improved discharge data, this study found the following optimised plant design parameters based on plant design discharge of 6.20 m3/s: Installed capacity of 10.20 MW; Annual energy production of 42 GWh; Capacity factor of 47.1%; 3 x Pelton wheel of 272 rpm speed, 2.1 m diameter, 2-nozzles of diameter 0.16 m each, 21 buckets of 0.58m width each; and 3 x 4 MVA generators of 50Hz, 22-poles, and 11kV.

Engineering and Technology JournalVol. 09(09)
University of Zambia (ZM)
Openalex Percentile: Top 83%
Cavitation Phenomena in Pumps
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.