Delays Factors for Construction Projects in South of Iraq

This study seeks to identify and categorize the factors responsible for delays in construction projects in southern Iraq. Using a sequential research approach that includes a literature review, interviews, and surveys, data were collected from 115 industry professionals, including clients, consultants, project managers, contractors, and engineers. The analysis utilized both descriptive and conclusive statistical methods, with a specific emphasis on the Spearman rank correlation coefficient to verify the reliability of the delay factor rankings. The research identified 45 major delay factors, with the most critical being global and local economic crises, bureaucracy and corruption, public holidays, delays in securing municipal permits, and frequent change orders initiated by clients. These factors were further classified into eight categories: inaccuracies in the tendering process, technical performance management, government interference, rework in construction practices, among others. The results indicate strong consensus among the different respondent groups regarding the main causes of project delays, as demonstrated by high correlation coefficients and a Chi-squared test confirming the agreement's significance. The findings provide valuable insights for practical applications and academic research, supporting the selection of project leaders, anticipating potential delays, and improving project management practices in Iraq. The study suggests future research should focus on strategic economic planning, exploring alternative funding sources, combating corruption, and implementing regulatory reforms to address the identified delay factors.

Authors

Institutions

Publication Details

Journal
Engineering and Technology Journal
Published
2024-09-09
DOI
https://doi.org/10.47191/etj/v9i09.11
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Delays Factors for Construction Projects in South of Iraq

Noor Ali Abdulridha, Mawahib A. Gata
Engineering and Technology Journal
Construction Project Management and Performance
article

Delays Factors for Construction Projects in South of Iraq

Noor Ali Abdulridha, Mawahib A. Gata
article en

Abstract

This study seeks to identify and categorize the factors responsible for delays in construction projects in southern Iraq. Using a sequential research approach that includes a literature review, interviews, and surveys, data were collected from 115 industry professionals, including clients, consultants, project managers, contractors, and engineers. The analysis utilized both descriptive and conclusive statistical methods, with a specific emphasis on the Spearman rank correlation coefficient to verify the reliability of the delay factor rankings. The research identified 45 major delay factors, with the most critical being global and local economic crises, bureaucracy and corruption, public holidays, delays in securing municipal permits, and frequent change orders initiated by clients. These factors were further classified into eight categories: inaccuracies in the tendering process, technical performance management, government interference, rework in construction practices, among others. The results indicate strong consensus among the different respondent groups regarding the main causes of project delays, as demonstrated by high correlation coefficients and a Chi-squared test confirming the agreement's significance. The findings provide valuable insights for practical applications and academic research, supporting the selection of project leaders, anticipating potential delays, and improving project management practices in Iraq. The study suggests future research should focus on strategic economic planning, exploring alternative funding sources, combating corruption, and implementing regulatory reforms to address the identified delay factors.

Engineering and Technology JournalVol. 09(09)
Thi Qar University (IQ)
Openalex Percentile: Top 80%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.