Cost and Time Analysis Using the Earned Value Analysis Method

Construction project management prioritizes the achievement of three main objectives: cost, quality, and time. This study evaluates a road widening project in Mojokerto Regency with a target completion time of 150 days. To prevent delays and cost overruns, researchers used the Earned Value method to identify early warnings regarding project performance. This method integrates time and cost values through measurements of Cost Variance (CV), Schedule Variance (SV), Cost Performance Index (CPI), Schedule Performance Index (SPI), Estimated at Completion (EAC), and Estimated Schedule at Completion (EAC). The research findings show that additional costs required (ETC) reached Rp 3,276,704,110.14, with additional time (ETS) up to week 12 being 87 days. The change in project costs (EAC) reached Rp 3,961,767,811.01 from the contract cost, while the project completion time (EAS) was 171 days. The analysis indicates that the construction service provider has implemented an efficient implementation method with consistent supervision, ensuring the smooth progress of the project.

Authors

Institutions

Publication Details

Journal
Eduvest - Journal Of Universal Studies
Published
2024-09-20
DOI
https://doi.org/10.59188/eduvest.v4i9.6402
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Cost and Time Analysis Using the Earned Value Analysis Method

Budi Witjaksana, Hanie Teki Tjendani, Sugeng Hariyadi
Eduvest - Journal Of Universal Studies
Occupational Health and Safety Management
article

Cost and Time Analysis Using the Earned Value Analysis Method

Budi Witjaksana, Hanie Teki Tjendani, Sugeng Hariyadi
article en

Abstract

Construction project management prioritizes the achievement of three main objectives: cost, quality, and time. This study evaluates a road widening project in Mojokerto Regency with a target completion time of 150 days. To prevent delays and cost overruns, researchers used the Earned Value method to identify early warnings regarding project performance. This method integrates time and cost values through measurements of Cost Variance (CV), Schedule Variance (SV), Cost Performance Index (CPI), Schedule Performance Index (SPI), Estimated at Completion (EAC), and Estimated Schedule at Completion (EAC). The research findings show that additional costs required (ETC) reached Rp 3,276,704,110.14, with additional time (ETS) up to week 12 being 87 days. The change in project costs (EAC) reached Rp 3,961,767,811.01 from the contract cost, while the project completion time (EAS) was 171 days. The analysis indicates that the construction service provider has implemented an efficient implementation method with consistent supervision, ensuring the smooth progress of the project.

Eduvest - Journal Of Universal StudiesVol. 4(9)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 71%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Cost and Time Analysis Using the Earned Value Analysis Method — Budi Witjaksana, Hanie Teki Tjendani, et al. · Eduvest - Journal Of Universal Studies (2024) | TGRS Research Map | TGRS