Optimizing Competency-Based Human Resource Allocation in Construction Project Scheduling: A Multi-Objective Meta-Heuristic Approach

Effective allocation of human resources to project activities is crucial in optimizing project schedules and resource utilization. This paper addresses the challenge of competency-based workforce allocation in construction project scheduling by integrating multi-criteria decision-making with meta-heuristic optimization. A three-objective mathematical planning model aimed at minimizing project completion time, reducing implementation costs, and enhancing workforce competency is proposed. By leveraging expert opinions and multi-criteria decision-making techniques the relevant competency criteria are identified and prioritized. Our approach involves solving a sample problem precisely using GAMS software and developing two meta-heuristic algorithms—Non-Dominated Sorting Genetic Algorithm (NSGA-II) and Multi-Objective Particle Swarm Optimization (MOPSO). The algorithms' parameters were optimized using Taguchi design techniques to ensure robust performance. The effectiveness of our proposed methods is validated by comparing their results with exact solutions and conducting extensive tests on large-scale problems. The results demonstrate that both meta-heuristic algorithms effectively address the competency-based allocation challenge, with NSGA-II showing superior performance in achieving optimal solutions. This study highlights the potential of integrating competency-based approaches with advanced optimization techniques to enhance project management in construction.

Authors

Institutions

Publication Details

Journal
Qubahan Academic Journal
Published
2024-09-27
DOI
https://doi.org/10.48161/qaj.v4n3a1027
Citations
4
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
1.96
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimizing Competency-Based Human Resource Allocation in Construction Project Scheduling: A Multi-Objective Meta-Heuristic Approach

Heidar Dashti Naserabadi, Mohammad Javad Taheri Amiri, Bahman Shojaei
4 citations
Qubahan Academic Journal
Resource-Constrained Project Scheduling
1.96
article

Optimizing Competency-Based Human Resource Allocation in Construction Project Scheduling: A Multi-Objective Meta-Heuristic Approach

Heidar Dashti Naserabadi, Mohammad Javad Taheri Amiri, Bahman Shojaei
article en
4 citations

Abstract

Effective allocation of human resources to project activities is crucial in optimizing project schedules and resource utilization. This paper addresses the challenge of competency-based workforce allocation in construction project scheduling by integrating multi-criteria decision-making with meta-heuristic optimization. A three-objective mathematical planning model aimed at minimizing project completion time, reducing implementation costs, and enhancing workforce competency is proposed. By leveraging expert opinions and multi-criteria decision-making techniques the relevant competency criteria are identified and prioritized. Our approach involves solving a sample problem precisely using GAMS software and developing two meta-heuristic algorithms—Non-Dominated Sorting Genetic Algorithm (NSGA-II) and Multi-Objective Particle Swarm Optimization (MOPSO). The algorithms' parameters were optimized using Taguchi design techniques to ensure robust performance. The effectiveness of our proposed methods is validated by comparing their results with exact solutions and conducting extensive tests on large-scale problems. The results demonstrate that both meta-heuristic algorithms effectively address the competency-based allocation challenge, with NSGA-II showing superior performance in achieving optimal solutions. This study highlights the potential of integrating competency-based approaches with advanced optimization techniques to enhance project management in construction.

Qubahan Academic JournalVol. 4(3)
Tabaran Institute of Higher Education (IR), Qom Islamic Azad University (IR), Islamic Azad University of Chalous (IR), Islamic Azad University of Tafresh (IR)
Openalex Percentile: Top 13%
Resource-Constrained Project Scheduling
1.96
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Optimizing Competency-Based Human Resource Allocation in Construction Project Scheduling: A Multi-Objective Meta-Heuristic Approach — Heidar Dashti Naserabadi, Mohammad Javad Taheri Amiri, et al. · Qubahan Academic Journal (2024) | TGRS Research Map | TGRS