Stochastic optimal scheduling of a combined wind-photovoltaic-CSP-fire system accounting for electrical heat conversion

Aiming at the consumption problem caused by the increasing scale of wind power and photovoltaic (PV) grid-connected, a multi-energy co-generation system is constructed with wind power, PV, concentrated solar power (CSP), and thermal power; in addition, in order to reduce the impact of the prediction errors of wind power, PV, and loads on the system’s economic operation, the photovoltaic and thermal power plants are used to provide the system's backup capacity together, and the opportunity constraint model of the reliability of the backup capacity is established, so as to satisfy the system reliability constraints at a certain higher confidence level; finally, a sampling-based deterministic transformation method is introduced to simplify the model. The model is simplified by introducing a sampling-based deterministic transformation method of opportunity constraint; finally, a stochastic optimal dispatch model of the combined wind-photovoltaic-CSP-fire system, which accounts for the conversion of electricity and heat, is constructed with the objective of minimising the integrated operating cost of the combined system, and the effectiveness of the proposed model is analysed by simulation verification.

Authors

Publication Details

Journal
Energy Informatics
Published
2024-09-27
DOI
https://doi.org/10.1186/s42162-024-00395-3
Citations
2
Primary Topic
Smart Grid Energy Management
Type
article
Field-Weighted Citation Impact
0.42
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Stochastic optimal scheduling of a combined wind-photovoltaic-CSP-fire system accounting for electrical heat conversion

Jiawen Sun, Mengke Liao, Hua Dong, Xinfu Song et al.
2 citations
Energy Informatics
Smart Grid Energy Management
0.42
article

Stochastic optimal scheduling of a combined wind-photovoltaic-CSP-fire system accounting for electrical heat conversion

Jiawen Sun, Mengke Liao, Hua Dong, Xinfu Song, Zhongzheng Li
article en
2 citations

Abstract

Aiming at the consumption problem caused by the increasing scale of wind power and photovoltaic (PV) grid-connected, a multi-energy co-generation system is constructed with wind power, PV, concentrated solar power (CSP), and thermal power; in addition, in order to reduce the impact of the prediction errors of wind power, PV, and loads on the system’s economic operation, the photovoltaic and thermal power plants are used to provide the system's backup capacity together, and the opportunity constraint model of the reliability of the backup capacity is established, so as to satisfy the system reliability constraints at a certain higher confidence level; finally, a sampling-based deterministic transformation method is introduced to simplify the model. The model is simplified by introducing a sampling-based deterministic transformation method of opportunity constraint; finally, a stochastic optimal dispatch model of the combined wind-photovoltaic-CSP-fire system, which accounts for the conversion of electricity and heat, is constructed with the objective of minimising the integrated operating cost of the combined system, and the effectiveness of the proposed model is analysed by simulation verification.

Energy InformaticsVol. 7(1)
Affordable and clean energy
Openalex Percentile: Top 38%
Smart Grid Energy Management
0.42
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.