Statistically Mitigating Subjective Estimates with PERT and Montecarlo

This paper introduces a methodology for advanced project duration estimation, integrating the Program Evaluation and Review Technique (PERT) with Monte Carlo simulation. It employs various distributions — normal and beta — to enhance the accuracy of task duration modeling based on initial three-point estimates. This aproach refines these distributions, establishing a robust mode while maintaining a consistent 90th- percentile confidence level. The study illustrates the feasibility of the implementation using accessible tools i.e., Google Sheets and Power BI, ensuring practicality in project management. The conclusion underscores improved accuracy and reliability in project duration estimates, enhancing risk management and decision- making throughout project execution.

Authors

Publication Details

Journal
International Journal of Innovative Science and Research Technology (IJISRT)
Published
2024-09-26
DOI
https://doi.org/10.38124/ijisrt/ijisrt24sep164
Citations
1
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.49
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Statistically Mitigating Subjective Estimates with PERT and Montecarlo

Abel J. Stephen
1 citations
International Journal of Innovative Science and Research Technology (IJISRT)
Resource-Constrained Project Scheduling
0.49
article

Statistically Mitigating Subjective Estimates with PERT and Montecarlo

Abel J. Stephen
article en
1 citations

Abstract

This paper introduces a methodology for advanced project duration estimation, integrating the Program Evaluation and Review Technique (PERT) with Monte Carlo simulation. It employs various distributions — normal and beta — to enhance the accuracy of task duration modeling based on initial three-point estimates. This aproach refines these distributions, establishing a robust mode while maintaining a consistent 90th- percentile confidence level. The study illustrates the feasibility of the implementation using accessible tools i.e., Google Sheets and Power BI, ensuring practicality in project management. The conclusion underscores improved accuracy and reliability in project duration estimates, enhancing risk management and decision- making throughout project execution.

International Journal of Innovative Science and Research Technology (IJISRT)
Openalex Percentile: Top 31%
Resource-Constrained Project Scheduling
0.49
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.