Visual versus Tabular Scheduling Programs

Effective scheduling in construction is crucial for ensuring timely project completion and maintaining budget control. Scheduling programs play an important role in this process by providing digital tools to develop, monitor, and adjust project timelines effectively. In the industry’s current method of practice, tabular scheduling programs are utilized that require users to enter task information and their relationships in a tabular format. Recently, a new scheduling program approach called visual scheduling has emerged that requires users to draw the network diagram to create the schedule. This paper presents an experimental study that evaluated the efficiency of schedule creation using a visual scheduling program compared to two tabular scheduling programs. The results show that the time spent creating a schedule using the visual scheduling program was significantly shorter than using tabular scheduling programs. Participants found visual scheduling easier to define tasks, define correlations, spot mistakes in the schedule, make changes to the schedule, and understand the overall schedule. The majority of the participants reported visual scheduling as a tool that allowed them to create schedules faster. They also found it to be a more intuitive scheduling tool and a method that can reduce the possibility of making mistakes during scheduling.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2024-09-26
DOI
https://doi.org/10.3390/buildings14103084
Primary Topic
Advanced Manufacturing and Logistics Optimization
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Visual versus Tabular Scheduling Programs

Bita Astaneh Asl, Tanmay Zakaria Tuscano
Buildings
Advanced Manufacturing and Logistics Optimization
article

Visual versus Tabular Scheduling Programs

Bita Astaneh Asl, Tanmay Zakaria Tuscano
article en

Abstract

Effective scheduling in construction is crucial for ensuring timely project completion and maintaining budget control. Scheduling programs play an important role in this process by providing digital tools to develop, monitor, and adjust project timelines effectively. In the industry’s current method of practice, tabular scheduling programs are utilized that require users to enter task information and their relationships in a tabular format. Recently, a new scheduling program approach called visual scheduling has emerged that requires users to draw the network diagram to create the schedule. This paper presents an experimental study that evaluated the efficiency of schedule creation using a visual scheduling program compared to two tabular scheduling programs. The results show that the time spent creating a schedule using the visual scheduling program was significantly shorter than using tabular scheduling programs. Participants found visual scheduling easier to define tasks, define correlations, spot mistakes in the schedule, make changes to the schedule, and understand the overall schedule. The majority of the participants reported visual scheduling as a tool that allowed them to create schedules faster. They also found it to be a more intuitive scheduling tool and a method that can reduce the possibility of making mistakes during scheduling.

BuildingsVol. 14(10)
California State University, East Bay (US)
California State University, East Bay
Openalex Percentile: Top 77%
Advanced Manufacturing and Logistics Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.