Actor–Critic Algorithm for the Dynamic Scheduling Problem of Unrelated Parallel Batch Machines

With the continuous development of the information industry, semiconductor manufacturing has become a key basic industry in the information age. Due to the demands of the process, there are more batch processes in the semiconductor manufacturing process, such as the aging test session of chips. In this paper, in the context of semiconductor manufacturing, we consider the unrelated parallel batch processing machine (UPBPM) scheduling problem in which jobs have different processing times, arrival times, sizes, and processing eligibility constraints, where the machines have different capacity constraints and the objective of minimizing the makespan. We propose the actor–critic algorithm, incorporating the Rolling Time Window (R-AC algorithm) to solve the UPBPM scheduling problem. Through simulation experiments, the R-AC algorithm outperforms the separate heuristic scheduling rules.

Authors

Institutions

Publication Details

Published
2024-09-23
DOI
https://doi.org/10.3390/engproc2024075012
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Actor–Critic Algorithm for the Dynamic Scheduling Problem of Unrelated Parallel Batch Machines

Mudassar Rauf, Yarong Chen, Xue Zhao
Scheduling and Optimization Algorithms
article

Actor–Critic Algorithm for the Dynamic Scheduling Problem of Unrelated Parallel Batch Machines

Mudassar Rauf, Yarong Chen, Xue Zhao
article en

Abstract

With the continuous development of the information industry, semiconductor manufacturing has become a key basic industry in the information age. Due to the demands of the process, there are more batch processes in the semiconductor manufacturing process, such as the aging test session of chips. In this paper, in the context of semiconductor manufacturing, we consider the unrelated parallel batch processing machine (UPBPM) scheduling problem in which jobs have different processing times, arrival times, sizes, and processing eligibility constraints, where the machines have different capacity constraints and the objective of minimizing the makespan. We propose the actor–critic algorithm, incorporating the Rolling Time Window (R-AC algorithm) to solve the UPBPM scheduling problem. Through simulation experiments, the R-AC algorithm outperforms the separate heuristic scheduling rules.

Wenzhou University (CN)
Openalex Percentile: Top 78%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Actor–Critic Algorithm for the Dynamic Scheduling Problem of Unrelated Parallel Batch Machines — Mudassar Rauf, Yarong Chen, et al. · (2024) | TGRS Research Map | TGRS