The performance of priority rules for the decentralized resource-constrained multi-project scheduling

Decentralized resource-constrained multi-project scheduling (DRCMPSP) is becoming increasingly common in construction, supply chains , and many other industrial disciplines. DRCMPSP faces difficult decisions in resolving resource conflicts to generate a baseline schedule to optimize global objectives. We propose an agent-based approach to address the DRCMPSP based on two global objectives: average project delay and total project delay. A heuristic based on the priority rule (PR) is developed to coordinate the global resource allocation . A comprehensive analysis of 30 PRs was conducted on 16,000 portfolios containing 48,000 projects . We confirmed that using the same PR to allocate global resources on all occasions often results in unnecessarily poor performance. The best PR depends on project and portfolio characteristics such as serial/parallel indicators, global resource distribution, and tightness. Moreover, the best PR differs from various perspectives (e.g., projects and portfolios). We summarized our results in three decision tables and further distilled these results for practical use, which only provide a rough estimate of the project and portfolio characteristics.

Authors

Institutions

Publication Details

Journal
Knowledge-Based Systems
Published
2024-09-19
DOI
https://doi.org/10.1016/j.knosys.2024.112530
Citations
2
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.98

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The performance of priority rules for the decentralized resource-constrained multi-project scheduling

Hongri Mao, Jianbo Yuan
2 citations
Knowledge-Based Systems
Resource-Constrained Project Scheduling
0.98
article

The performance of priority rules for the decentralized resource-constrained multi-project scheduling

Hongri Mao, Jianbo Yuan
article en
2 citations

Abstract

Decentralized resource-constrained multi-project scheduling (DRCMPSP) is becoming increasingly common in construction, supply chains , and many other industrial disciplines. DRCMPSP faces difficult decisions in resolving resource conflicts to generate a baseline schedule to optimize global objectives. We propose an agent-based approach to address the DRCMPSP based on two global objectives: average project delay and total project delay. A heuristic based on the priority rule (PR) is developed to coordinate the global resource allocation . A comprehensive analysis of 30 PRs was conducted on 16,000 portfolios containing 48,000 projects . We confirmed that using the same PR to allocate global resources on all occasions often results in unnecessarily poor performance. The best PR depends on project and portfolio characteristics such as serial/parallel indicators, global resource distribution, and tightness. Moreover, the best PR differs from various perspectives (e.g., projects and portfolios). We summarized our results in three decision tables and further distilled these results for practical use, which only provide a rough estimate of the project and portfolio characteristics.

Knowledge-Based SystemsVol. 304
Changsha University of Science and Technology (CN)
National Natural Science Foundation of China, Hunan Provincial Innovation Foundation for Postgraduate
Openalex Percentile: Top 21%
Resource-Constrained Project Scheduling
0.98
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

The performance of priority rules for the decentralized resource-constrained multi-project scheduling — Hongri Mao, Jianbo Yuan · Knowledge-Based Systems (2024) | TGRS Research Map | TGRS