Biaya dan Waktu pada Pelaksanaan Pekerjaan Struktur Balok Precast dan Balok Konvensional

Concrete is a construction material that is widely used in Indonesia, when compared to the use of wood and steel materials, there are two methods of concrete work, namely the conventional method and the precast method. In the Kuta Art Market Development Project there are several blocks using the conventional method and some using the precast method. How to compare the cost and time of conventional beam work and the precast method and which method is more effective to use. To be able to determine the choice of the right method to use, an analysis of costs and implementation time is carried out. Furthermore, the results of the analysis are compared so as to get an effective method to use. From the results of the analysis carried out at the Kuta Art Market Development Project, a comparison of costs and implementation time obtained that the total cost for the work of 5 conventional blocks was IDR 47,656,004.04 and the time needed to complete the work of 5 conventional blocks was 5 days. Whereas the total cost required for the work of 5 precast beams is Rp. 46,006,742.42 and the time required to complete the work of 5 precast beams is 4.09 days. When compared, the cost of precast beam work is Rp. 1,649,301.32 (3.5%) cheaper and the execution time for precast beam work is 0.91 days (18%) faster than conventional beam work.

Authors

Institutions

Publication Details

Journal
Jurnal Talenta Sipil
Published
2024-08-11
DOI
https://doi.org/10.33087/talentasipil.v7i2.628
Primary Topic
Geotechnical and construction materials studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Biaya dan Waktu pada Pelaksanaan Pekerjaan Struktur Balok Precast dan Balok Konvensional

Fajar Surya Herlambang, I.G.A. Neny Purnawirati
Jurnal Talenta Sipil
Geotechnical and construction materials studies
article

Biaya dan Waktu pada Pelaksanaan Pekerjaan Struktur Balok Precast dan Balok Konvensional

Fajar Surya Herlambang, I.G.A. Neny Purnawirati
article en

Abstract

Concrete is a construction material that is widely used in Indonesia, when compared to the use of wood and steel materials, there are two methods of concrete work, namely the conventional method and the precast method. In the Kuta Art Market Development Project there are several blocks using the conventional method and some using the precast method. How to compare the cost and time of conventional beam work and the precast method and which method is more effective to use. To be able to determine the choice of the right method to use, an analysis of costs and implementation time is carried out. Furthermore, the results of the analysis are compared so as to get an effective method to use. From the results of the analysis carried out at the Kuta Art Market Development Project, a comparison of costs and implementation time obtained that the total cost for the work of 5 conventional blocks was IDR 47,656,004.04 and the time needed to complete the work of 5 conventional blocks was 5 days. Whereas the total cost required for the work of 5 precast beams is Rp. 46,006,742.42 and the time required to complete the work of 5 precast beams is 4.09 days. When compared, the cost of precast beam work is Rp. 1,649,301.32 (3.5%) cheaper and the execution time for precast beam work is 0.91 days (18%) faster than conventional beam work.

Jurnal Talenta SipilVol. 7(2)
Politeknik Negeri Semarang
Industry, innovation and infrastructure
Openalex Percentile: Top 82%
Geotechnical and construction materials studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.