Feasibility of Placing Large-Scale Electrolyzers in Domestic Power Plants
The aim of the article is to verify the feasibility of placing large-scale (up to 100 MWe) water electrolysis technology unit inside, or in the proximity of a domestic nuclear power plant. The possible location is investigated from technological, logistic and nuclear-safety points of view.
Authors
- Martin Šilhan
- Pavla Lukášová (ORCID: https://orcid.org/0009-0000-6945-6821)
- Václav Hakl
- Jaroslav Stoklasa
Institutions
- Research Centre Rez (CZ)
- Nuclear Research Institute Rez (Czechia) (CZ)
Publication Details
- Journal
- Chemické listy
- Published
- 2024-09-15
- DOI
- https://doi.org/10.54779/chl20240491
- Primary Topic
- Industrial Engineering and Technologies
- Type
- article
- Field-Weighted Citation Impact
- 0.00