Multiobjective unrelated parallel machines scheduling problem with periodic maintenance activities and dependent processing times

Purpose The purpose of this research is to address the complex multiobjective unrelated parallel machine scheduling problem with real-world constraints, including sequence-dependent setup times and periodic machine maintenance. The primary goal is to minimize total tardiness, earliness and total completion times simultaneously. This study aims to provide effective solution methods, including a Mixed-Integer Programming (MIP) model, an Epsilon-constraint method and the Nondominated Sorting Genetic Algorithm (NSGA-II), to offer valuable insights into solving large-sized instances of this challenging problem. Design/methodology/approach This study addresses a multiobjective unrelated parallel machine scheduling problem with sequence-dependent setup times and periodic machine maintenance activities. An MIP model is introduced to formulate the problem, and an Epsilon-constraint method is applied for a solution. To handle the NP-hard nature of the problem for larger instances, an NSGA-II is developed. The research involves the creation of 45 problem instances for computational experiments, which evaluate the performance of the algorithms in terms of proposed measures. Findings The research findings demonstrate the effectiveness of the proposed solution approaches for the multiobjective unrelated parallel machine scheduling problem. Computational experiments on 45 generated problem instances reveal that the NSGA-II algorithm outperforms the Epsilon-constraint method, particularly for larger instances. The algorithms successfully minimize total tardiness, earliness and total completion times, showcasing their practical applicability and efficiency in handling real-world scheduling scenarios. Originality/value This study contributes original value by addressing a complex multiobjective unrelated parallel machine scheduling problem with real-world constraints, including sequence-dependent setup times and periodic machine maintenance activities. The introduction of an MIP model, the application of the Epsilon-constraint method and the development of the NSGA-II algorithm offer innovative approaches to solving this NP-hard problem. The research provides valuable insights into efficient scheduling methods applicable in various industries, enhancing decision-making processes and operational efficiency.

Authors

Institutions

Publication Details

Journal
Journal of Modelling in Management
Published
2024-09-13
DOI
https://doi.org/10.1108/jm2-09-2023-0198
Citations
3
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
1.05
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Multiobjective unrelated parallel machines scheduling problem with periodic maintenance activities and dependent processing times

Youness Javid, Mohammad Yaghtin
3 citations
Journal of Modelling in Management
Scheduling and Optimization Algorithms
1.05
article

Multiobjective unrelated parallel machines scheduling problem with periodic maintenance activities and dependent processing times

Youness Javid, Mohammad Yaghtin
article en
3 citations

Abstract

Purpose The purpose of this research is to address the complex multiobjective unrelated parallel machine scheduling problem with real-world constraints, including sequence-dependent setup times and periodic machine maintenance. The primary goal is to minimize total tardiness, earliness and total completion times simultaneously. This study aims to provide effective solution methods, including a Mixed-Integer Programming (MIP) model, an Epsilon-constraint method and the Nondominated Sorting Genetic Algorithm (NSGA-II), to offer valuable insights into solving large-sized instances of this challenging problem. Design/methodology/approach This study addresses a multiobjective unrelated parallel machine scheduling problem with sequence-dependent setup times and periodic machine maintenance activities. An MIP model is introduced to formulate the problem, and an Epsilon-constraint method is applied for a solution. To handle the NP-hard nature of the problem for larger instances, an NSGA-II is developed. The research involves the creation of 45 problem instances for computational experiments, which evaluate the performance of the algorithms in terms of proposed measures. Findings The research findings demonstrate the effectiveness of the proposed solution approaches for the multiobjective unrelated parallel machine scheduling problem. Computational experiments on 45 generated problem instances reveal that the NSGA-II algorithm outperforms the Epsilon-constraint method, particularly for larger instances. The algorithms successfully minimize total tardiness, earliness and total completion times, showcasing their practical applicability and efficiency in handling real-world scheduling scenarios. Originality/value This study contributes original value by addressing a complex multiobjective unrelated parallel machine scheduling problem with real-world constraints, including sequence-dependent setup times and periodic machine maintenance activities. The introduction of an MIP model, the application of the Epsilon-constraint method and the development of the NSGA-II algorithm offer innovative approaches to solving this NP-hard problem. The research provides valuable insights into efficient scheduling methods applicable in various industries, enhancing decision-making processes and operational efficiency.

Journal of Modelling in ManagementVol. 20(2)
Kharazmi University (IR)
Openalex Percentile: Top 20%
Scheduling and Optimization Algorithms
1.05
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.