Importance of long-term monitoring of the earth dams

As structures of high risk, with catastrophic consequences in case of exceeding the limit states, dams must be continuously monitored in order to timely identify potential problems and to take preventive measures to preserve the structural integrity of the dams. This is especially the case with earth dams, which are extremely sensitive to ubiquitous changes in climate patterns. The paper describes the techniques of long-term monitoring of earth dams and gives a summary of the possible monitoring equipment used. Through the example of the Butoniga dam in Istria, the importance of long-term monitoring, as a vital part of the dam’s functionality and safety, is demonstrated. Monitoring of the Butoniga dam, with a total height of 23 m and a reservoir volume of 20 million m3, began during construction from 1979 to 1986 and continued in operation until today, with the monitoring system being continuously upgraded.

Authors

Publication Details

Published
2024-09-12
DOI
https://doi.org/10.5592/co/phdsym.2024.4
Citations
1
Primary Topic
Dam Engineering and Safety
Type
article
Field-Weighted Citation Impact
0.26
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Importance of long-term monitoring of the earth dams

Goran Grget, Mario Bačić
1 citations
Dam Engineering and Safety
0.26
article

Importance of long-term monitoring of the earth dams

Goran Grget, Mario Bačić
article en
1 citations

Abstract

As structures of high risk, with catastrophic consequences in case of exceeding the limit states, dams must be continuously monitored in order to timely identify potential problems and to take preventive measures to preserve the structural integrity of the dams. This is especially the case with earth dams, which are extremely sensitive to ubiquitous changes in climate patterns. The paper describes the techniques of long-term monitoring of earth dams and gives a summary of the possible monitoring equipment used. Through the example of the Butoniga dam in Istria, the importance of long-term monitoring, as a vital part of the dam’s functionality and safety, is demonstrated. Monitoring of the Butoniga dam, with a total height of 23 m and a reservoir volume of 20 million m3, began during construction from 1979 to 1986 and continued in operation until today, with the monitoring system being continuously upgraded.

Openalex Percentile: Top 45%
Dam Engineering and Safety
0.26
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.