Analisis Percepatan Pelaksanaan Pekerjaan pada Proyek Pembangunan Safety Riding Centre

The Accelerating project completion must be done with proper planning. One of the alternatives that can be used to support the acceleration of work activities is by adding manpower and working hours, in order to address delays in a project. To achieve maximum benefits without compromising workplace safety and job quality. The aim of this research is to analyze the acceleration of the implementation of the safety riding center project by adding optimal manpower and working hours. The method used in this research is a descriptive method with a case study approach. The Crashing method is used to expedite the delay in the riding center project using Microsoft Office Project 2016 as a data processing tool. After analyzing the data, it can be concluded that there are 3 critical paths that affect the implementation of the safety riding center project, and adding optimal manpower and working hours is performed. The results obtained after the analysis show that the upper structure work has the longest critical path with an initial completion time of 161 days, which is accelerated by 38 days to become 123 days earlier with the addition of 8 workers. With an initial cost of 4,519,890,373 becoming 4,519,965,373. The higher the cost incurred, the faster the delayed work is completed.

Authors

Publication Details

Journal
Pustaka Jurnal Ilmu-Ilmu Budaya
Published
2024-09-01
DOI
https://doi.org/10.24843/pjiib.2024.v24.i02.p03
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analisis Percepatan Pelaksanaan Pekerjaan pada Proyek Pembangunan Safety Riding Centre

Dorlan Siregar
Pustaka Jurnal Ilmu-Ilmu Budaya
Occupational Health and Safety Management
article

Analisis Percepatan Pelaksanaan Pekerjaan pada Proyek Pembangunan Safety Riding Centre

Dorlan Siregar
article en

Abstract

The Accelerating project completion must be done with proper planning. One of the alternatives that can be used to support the acceleration of work activities is by adding manpower and working hours, in order to address delays in a project. To achieve maximum benefits without compromising workplace safety and job quality. The aim of this research is to analyze the acceleration of the implementation of the safety riding center project by adding optimal manpower and working hours. The method used in this research is a descriptive method with a case study approach. The Crashing method is used to expedite the delay in the riding center project using Microsoft Office Project 2016 as a data processing tool. After analyzing the data, it can be concluded that there are 3 critical paths that affect the implementation of the safety riding center project, and adding optimal manpower and working hours is performed. The results obtained after the analysis show that the upper structure work has the longest critical path with an initial completion time of 161 days, which is accelerated by 38 days to become 123 days earlier with the addition of 8 workers. With an initial cost of 4,519,890,373 becoming 4,519,965,373. The higher the cost incurred, the faster the delayed work is completed.

Pustaka Jurnal Ilmu-Ilmu BudayaVol. 24(2)
Openalex Percentile: Top 74%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.