Minimum Distance Calculation Method for Collision Issues in Lifting Construction Scenarios

In the construction process of prefabricated buildings, collision detection of the tower crane’s lifting path is of paramount importance. During the actual operation of a tower crane, attention is not only given to whether components collide with obstacles but also to calculating the minimum distance from hoisted components to obstacles and identifying the closest obstacle’s ID. This information provides operators or path planners with valuable insights to prevent accidents. This study addresses this issue by proposing a minimum distance calculation method for collision issues in lifting construction scenarios. First, based on the motion characteristics of tower crane hoisting, we employ vertically aligned oriented bounding boxes (VA-OBB) to fit the structural elements in the scene. VA-OBBs are compact bounding volumes (BV) with a rapid update rate. Subsequently, a method for calculating the minimum distance between VA-OBBs is introduced. With this approach, specific calculations are proposed for different risk scenarios in lifting construction. Using real building information modeling (BIM) data from a prefabricated construction scenario as a case study, we conducted an analysis that recorded the minimum distance information throughout the lifting path. This aids in analyzing the causes of accidents and rectifying unsafe path planning. Finally, we evaluate the accuracy and efficiency of the algorithm. Empirical results demonstrate that the algorithm can perform real-time and accurate collision calculations during the hoisting process of prefabricated construction. Additionally, this paper discusses the limitations of the research method and suggests directions for future improvements, providing a viable solution for collision issues in the field of hoisting construction.

Authors

Institutions

Publication Details

Journal
Journal of Computing in Civil Engineering
Published
2024-09-10
DOI
https://doi.org/10.1061/jccee5.cpeng-5914
Citations
3
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.80
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Minimum Distance Calculation Method for Collision Issues in Lifting Construction Scenarios

Bin Yang, H. M. Zhang, Zhirong Shen
3 citations
Journal of Computing in Civil Engineering
BIM and Construction Integration
0.80
article

Minimum Distance Calculation Method for Collision Issues in Lifting Construction Scenarios

Bin Yang, H. M. Zhang, Zhirong Shen
article en
3 citations

Abstract

In the construction process of prefabricated buildings, collision detection of the tower crane’s lifting path is of paramount importance. During the actual operation of a tower crane, attention is not only given to whether components collide with obstacles but also to calculating the minimum distance from hoisted components to obstacles and identifying the closest obstacle’s ID. This information provides operators or path planners with valuable insights to prevent accidents. This study addresses this issue by proposing a minimum distance calculation method for collision issues in lifting construction scenarios. First, based on the motion characteristics of tower crane hoisting, we employ vertically aligned oriented bounding boxes (VA-OBB) to fit the structural elements in the scene. VA-OBBs are compact bounding volumes (BV) with a rapid update rate. Subsequently, a method for calculating the minimum distance between VA-OBBs is introduced. With this approach, specific calculations are proposed for different risk scenarios in lifting construction. Using real building information modeling (BIM) data from a prefabricated construction scenario as a case study, we conducted an analysis that recorded the minimum distance information throughout the lifting path. This aids in analyzing the causes of accidents and rectifying unsafe path planning. Finally, we evaluate the accuracy and efficiency of the algorithm. Empirical results demonstrate that the algorithm can perform real-time and accurate collision calculations during the hoisting process of prefabricated construction. Additionally, this paper discusses the limitations of the research method and suggests directions for future improvements, providing a viable solution for collision issues in the field of hoisting construction.

Journal of Computing in Civil EngineeringVol. 38(6)
Tongji University (CN)
Climate action
Openalex Percentile: Top 29%
BIM and Construction Integration
0.80
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Minimum Distance Calculation Method for Collision Issues in Lifting Construction Scenarios — Bin Yang, H. M. Zhang, et al. · Journal of Computing in Civil Engineering (2024) | TGRS Research Map | TGRS