Schematic risk management in solicited and unsolicited project

The Indonesian government is currently carrying out massive infrastructure development, with a budget exceeding 10. Risk mapping based on good risk management is crucial for stakeholders in organizing construction projects. Projects financed by government, whether solicited or unsolicited schemes, should also include risk mapping to add value and foster partnerships. Therefore, this study aimed to develop a risk management model for solicited and unsolicited projects, focusing on the collaborative management system among stakeholders in government-financed projects. Risk review was conducted from various stakeholders’ perspectives, examining the impacts and potential losses to manage uncertainty and reduce losses for relevant parties. Furthermore, qualitative analysis was conducted using Focus Group Discussion (FGD) and in-depth interviews. The results showed that partnering-based risk management with risk sharing in solicited and unsolicited projects had similarities with Integrated Project Delivery (IPD). This approach provided benefits and value by developing various innovations in the project life cycle.

Authors

Institutions

Publication Details

Journal
Journal of Infrastructure Policy and Development
Published
2024-09-05
DOI
https://doi.org/10.24294/jipd.v8i9.5472
Citations
1
Primary Topic
Software Engineering Techniques and Practices
Type
article
Field-Weighted Citation Impact
0.78
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Schematic risk management in solicited and unsolicited project

Naniek Widayati, Rizal Z. Tamin, Mochamad Agung Wibowo, Endah Murtiana Sari et al.
1 citations
Journal of Infrastructure Policy and Development
Software Engineering Techniques and Practices
0.78
article

Schematic risk management in solicited and unsolicited project

Naniek Widayati, Rizal Z. Tamin, Mochamad Agung Wibowo, Endah Murtiana Sari, Mustafa Nahdi, Najid Najid
article en
1 citations

Abstract

The Indonesian government is currently carrying out massive infrastructure development, with a budget exceeding 10. Risk mapping based on good risk management is crucial for stakeholders in organizing construction projects. Projects financed by government, whether solicited or unsolicited schemes, should also include risk mapping to add value and foster partnerships. Therefore, this study aimed to develop a risk management model for solicited and unsolicited projects, focusing on the collaborative management system among stakeholders in government-financed projects. Risk review was conducted from various stakeholders’ perspectives, examining the impacts and potential losses to manage uncertainty and reduce losses for relevant parties. Furthermore, qualitative analysis was conducted using Focus Group Discussion (FGD) and in-depth interviews. The results showed that partnering-based risk management with risk sharing in solicited and unsolicited projects had similarities with Integrated Project Delivery (IPD). This approach provided benefits and value by developing various innovations in the project life cycle.

Journal of Infrastructure Policy and DevelopmentVol. 8(9)
Tarumanagara University (ID), Diponegoro University (ID), Bandung Institute of Technology (ID), Institut Manajemen Koperasi Indonesia (ID)
Openalex Percentile: Top 21%
Software Engineering Techniques and Practices
0.78
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.