Adding Objectivity to Alignment Studies—A Successful Recipe for Two Case Study Examples

Selecting an alignment in progressively developing corridors becomes increasingly more challenging every day. Property owners are less willing to grant easements and developers do not want to give up real estate, or for their developments to be disrupted by the process. In addition, adequate space for permanent and construction easements is very limited within these busy areas. These factors make justifying alignment paths, the workspace needed, and the project’s purpose of critical importance. Adequate justification of a selected alignment and associated easements is not only important to help explain the benefits of the project to impacted owners, but also to protect and justify the project should an eminent domain process be required. This paper will present a method developed to objectively analyze various alignment alternatives for two different types of projects: 10 mi (16.1 km) of 24-in. (610 mm) to 42-in. (1,067 mm) transmission main and 3 mi (4.8 km) of parallel 36-in. (915 mm) force main.

Authors

Institutions

Publication Details

Published
2024-08-30
DOI
https://doi.org/10.1061/9780784485569.039
Primary Topic
Psychometric Methodologies and Testing
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Adding Objectivity to Alignment Studies—A Successful Recipe for Two Case Study Examples

Kyle Sanderson, Shelby Warchesik, Jenifer Tatum, Geleany Morales-Carrero et al.
Psychometric Methodologies and Testing
article

Adding Objectivity to Alignment Studies—A Successful Recipe for Two Case Study Examples

Kyle Sanderson, Shelby Warchesik, Jenifer Tatum, Geleany Morales-Carrero, Walter Norwood
article en

Abstract

Selecting an alignment in progressively developing corridors becomes increasingly more challenging every day. Property owners are less willing to grant easements and developers do not want to give up real estate, or for their developments to be disrupted by the process. In addition, adequate space for permanent and construction easements is very limited within these busy areas. These factors make justifying alignment paths, the workspace needed, and the project’s purpose of critical importance. Adequate justification of a selected alignment and associated easements is not only important to help explain the benefits of the project to impacted owners, but also to protect and justify the project should an eminent domain process be required. This paper will present a method developed to objectively analyze various alignment alternatives for two different types of projects: 10 mi (16.1 km) of 24-in. (610 mm) to 42-in. (1,067 mm) transmission main and 3 mi (4.8 km) of parallel 36-in. (915 mm) force main.

Texas Water Development Board (US)
Reduced inequalities
Openalex Percentile: Top 83%
Psychometric Methodologies and Testing
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Adding Objectivity to Alignment Studies—A Successful Recipe for Two Case Study Examples — Kyle Sanderson, Shelby Warchesik, et al. · (2024) | TGRS Research Map | TGRS