Innovative Pipeline Design Solves the Problem of Seismic Reliability on a Constrained Urban Site at San Francisco’s New State-of-the-Art Headworks

The San Francisco Public Utilities Commission (SFPUC) initiated the design and construction of a 250 MGD all-weather headworks to improve wastewater treatment reliability and infrastructure flexibility in San Francisco, California. A critical objective of the project was rerouting the system’s 72-in. channel force main (CFM) to feed the new headworks using a three-story steel moment frame structure. Carollo Engineers, Inc. evaluated several alternatives and recommended a custom-built Victaulic dynamic movement joint (DMJ) to relieve stresses on the pipeline and its supporting structures. This innovative approach helped to accommodate differential movement between the pipe rack and rigid concrete structures without significant damage to piping or supporting structures.

Authors

Institutions

Publication Details

Published
2024-08-30
DOI
https://doi.org/10.1061/9780784485569.068
Primary Topic
Geotechnical Engineering and Underground Structures
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Innovative Pipeline Design Solves the Problem of Seismic Reliability on a Constrained Urban Site at San Francisco’s New State-of-the-Art Headworks

Mike Dadik, Luke Prinsloo, Kaushik V. Punyamurtula, Jignesh Desai
Geotechnical Engineering and Underground Structures
article

Innovative Pipeline Design Solves the Problem of Seismic Reliability on a Constrained Urban Site at San Francisco’s New State-of-the-Art Headworks

Mike Dadik, Luke Prinsloo, Kaushik V. Punyamurtula, Jignesh Desai
article en

Abstract

The San Francisco Public Utilities Commission (SFPUC) initiated the design and construction of a 250 MGD all-weather headworks to improve wastewater treatment reliability and infrastructure flexibility in San Francisco, California. A critical objective of the project was rerouting the system’s 72-in. channel force main (CFM) to feed the new headworks using a three-story steel moment frame structure. Carollo Engineers, Inc. evaluated several alternatives and recommended a custom-built Victaulic dynamic movement joint (DMJ) to relieve stresses on the pipeline and its supporting structures. This innovative approach helped to accommodate differential movement between the pipe rack and rigid concrete structures without significant damage to piping or supporting structures.

California Public Utilities Commission (US)
Sustainable cities and communities
Openalex Percentile: Top 84%
Geotechnical Engineering and Underground Structures
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Innovative Pipeline Design Solves the Problem of Seismic Reliability on a Constrained Urban Site at San Francisco’s New State-of-the-Art Headworks — Mike Dadik, Luke Prinsloo, et al. · (2024) | TGRS Research Map | TGRS