Collaborative Procurement and Risk Management of Soft Ground Tunnels for the Integrated Pipeline Project in Texas

The Tarrant Regional Water District (TRWD) and the City of Dallas Water Utilities (DWU) are in process of developing a 350 MGD water transmission system known as the Integrated Pipeline Project (IPL). Considering various project conditions, a set of particularly risky tunnels was combined into the PL19TUN project—a component project of the overall IPL. To mitigate against these risks, the Owner’s Project Team (OPT) developed a unique procurement strategy consisting of prequalification, collaborative workshops, and a competitive sealed proposal (CSP) process which resulted in a refined project scope and the selection by best value ranking of a qualified contractor to construct the project. This paper will discuss project conditions, constructability reviews, the collaborative CSP procurement, and risk management for this interesting project.

Authors

Institutions

Publication Details

Published
2024-08-30
DOI
https://doi.org/10.1061/9780784485576.052
Primary Topic
Geotechnical Engineering and Underground Structures
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Collaborative Procurement and Risk Management of Soft Ground Tunnels for the Integrated Pipeline Project in Texas

Coy Veach, Shelly Hattan, Robert Allen, Ed Weaver et al.
Geotechnical Engineering and Underground Structures
article

Collaborative Procurement and Risk Management of Soft Ground Tunnels for the Integrated Pipeline Project in Texas

Coy Veach, Shelly Hattan, Robert Allen, Ed Weaver, Matt Gaughan, Charles A. Cameron, Kurt Sanders, Thomas Kwiatkowski
article en

Abstract

The Tarrant Regional Water District (TRWD) and the City of Dallas Water Utilities (DWU) are in process of developing a 350 MGD water transmission system known as the Integrated Pipeline Project (IPL). Considering various project conditions, a set of particularly risky tunnels was combined into the PL19TUN project—a component project of the overall IPL. To mitigate against these risks, the Owner’s Project Team (OPT) developed a unique procurement strategy consisting of prequalification, collaborative workshops, and a competitive sealed proposal (CSP) process which resulted in a refined project scope and the selection by best value ranking of a qualified contractor to construct the project. This paper will discuss project conditions, constructability reviews, the collaborative CSP procurement, and risk management for this interesting project.

Agile Mind (US), Tarrant County College (US)
Industry, innovation and infrastructure
Openalex Percentile: Top 84%
Geotechnical Engineering and Underground Structures
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.