Force Main Rehabilitation Program for North Charleston Sewer District

The North Charleston Sewer District initiated a program in 2021 to rehabilitate its largest force mains with cured-in-place pipe (CIPP) methodology. The force mains were associated with their regional pump stations: Ingleside, Northwoods, Turkey Creek, and Noisette. The oldest force main (FM), Noisette, was constructed in the 1960s and has exceeded its useful service life. The project was bid in January of 2022. The preconstruction conference was conducted in late April 2022, but the commencement of construction was delayed until the end of October 2022, due to long delivery times for pipes, valves, fittings, and other materials. The rehabilitation of the Northwoods, Turkey Creek, and Noisette FMs is complete. The Ingleside rehabilitation should be completed by the end of 2024. This case study focuses on the interesting, unique challenges met during the project.

Authors

Institutions

Publication Details

Published
2024-08-30
DOI
https://doi.org/10.1061/9780784485576.036
Primary Topic
Geotechnical Engineering and Underground Structures
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Force Main Rehabilitation Program for North Charleston Sewer District

Phillip T. Sexton, James C. Reigart
Geotechnical Engineering and Underground Structures
article

Force Main Rehabilitation Program for North Charleston Sewer District

Phillip T. Sexton, James C. Reigart
article en

Abstract

The North Charleston Sewer District initiated a program in 2021 to rehabilitate its largest force mains with cured-in-place pipe (CIPP) methodology. The force mains were associated with their regional pump stations: Ingleside, Northwoods, Turkey Creek, and Noisette. The oldest force main (FM), Noisette, was constructed in the 1960s and has exceeded its useful service life. The project was bid in January of 2022. The preconstruction conference was conducted in late April 2022, but the commencement of construction was delayed until the end of October 2022, due to long delivery times for pipes, valves, fittings, and other materials. The rehabilitation of the Northwoods, Turkey Creek, and Noisette FMs is complete. The Ingleside rehabilitation should be completed by the end of 2024. This case study focuses on the interesting, unique challenges met during the project.

College of Charleston (US)
Openalex Percentile: Top 84%
Geotechnical Engineering and Underground Structures
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.