Rust to Wealth: Rehabilitation of Steel Pipes Using Carbon Fiber Reinforced Polymer Method

This paper focuses on the rehabilitation of steel stormwater discharge pipelines from a levee sump pump station. Irving Flood Control District Section III (IFCD-3) maintains 5.5 mi of waterways in Irving, Texas. The station’s six welded steel pipelines, constructed in 1979, exhibit significant corrosion, requiring repair or replacement. IFCD-3 contracted with Halff to develop a rehabilitation plan, exploring options like conventional replacement or internal rehabilitation using carbon fiber reinforced polymer (CFRP). The recommendation to apply internal CFRP rehabilitation considered factors, such as shutdown needs, internal pressure capacity, corrosion rate, and costs. Since CFRP involves manual application, the pipelines will be rehabilitated in two segments with access points for man-entry and ventilation. Competitive sealed bidding ensued with two contractors submitting bids. The recommended solution aims to maintain the integrity of the pipelines, supporting IFCD-3 in its regional flood protection efforts.

Authors

Institutions

Publication Details

Published
2024-08-30
DOI
https://doi.org/10.1061/9780784485576.061
Citations
1
Primary Topic
Geotechnical Engineering and Underground Structures
Type
article
Field-Weighted Citation Impact
0.26
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Rust to Wealth: Rehabilitation of Steel Pipes Using Carbon Fiber Reinforced Polymer Method

Tim Benefiel, Roza Fereidoonfar, Dallas Burke, Parker Moore et al.
1 citations
Geotechnical Engineering and Underground Structures
0.26
article

Rust to Wealth: Rehabilitation of Steel Pipes Using Carbon Fiber Reinforced Polymer Method

Tim Benefiel, Roza Fereidoonfar, Dallas Burke, Parker Moore, Ben Stephens
article en
1 citations

Abstract

This paper focuses on the rehabilitation of steel stormwater discharge pipelines from a levee sump pump station. Irving Flood Control District Section III (IFCD-3) maintains 5.5 mi of waterways in Irving, Texas. The station’s six welded steel pipelines, constructed in 1979, exhibit significant corrosion, requiring repair or replacement. IFCD-3 contracted with Halff to develop a rehabilitation plan, exploring options like conventional replacement or internal rehabilitation using carbon fiber reinforced polymer (CFRP). The recommendation to apply internal CFRP rehabilitation considered factors, such as shutdown needs, internal pressure capacity, corrosion rate, and costs. Since CFRP involves manual application, the pipelines will be rehabilitated in two segments with access points for man-entry and ventilation. Competitive sealed bidding ensued with two contractors submitting bids. The recommended solution aims to maintain the integrity of the pipelines, supporting IFCD-3 in its regional flood protection efforts.

The University of Texas at Dallas (US), Dallas County (US), Department of Water (AU)
Openalex Percentile: Top 45%
Geotechnical Engineering and Underground Structures
0.26
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.