The Art of Managing Contracts: Insights from the City of Toronto Ashbridges Bay Treatment Plant Outfall

Toronto Water’s Ashbridges Bay Treatment Plant Outfall (ABTPO) project will be the largest wastewater treatment plant effluent outfall in Canada. This paper discusses contract administration challenges encountered throughout the ABTPO construction phase. Project-specific construction management approaches, issues, and lessons learned are explored, including quality, schedule, risk and claims management, as well as the application of a Dispute Review Board (DRB). Owner and Consultant perspectives discuss how claims were successfully resolved for ABTPO. Contract administration insights for major disputes are presented, including a stuck bucket during shaft secant pile installation, three separate Differing Site Conditions (DSC) events involving unexpected adverse ground conditions with water inflows at greater than 400 lpm during Tunnel Boring Machine (TBM) tunnelling, and off-shore work claims involving riser installation DSC and marine weather conditions (e.g., adverse wind and waves). Lessons learned from successfully resolving these claims are also presented.

Authors

Institutions

Publication Details

Published
2024-08-30
DOI
https://doi.org/10.1061/9780784485576.054
Primary Topic
Law, Economics, and Judicial Systems
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The Art of Managing Contracts: Insights from the City of Toronto Ashbridges Bay Treatment Plant Outfall

Vlad Petran, Justyna Kempa-Teper, Kevin Waher, Andre Solecki et al.
Law, Economics, and Judicial Systems
article

The Art of Managing Contracts: Insights from the City of Toronto Ashbridges Bay Treatment Plant Outfall

Vlad Petran, Justyna Kempa-Teper, Kevin Waher, Andre Solecki, R. H. Morales
article en

Abstract

Toronto Water’s Ashbridges Bay Treatment Plant Outfall (ABTPO) project will be the largest wastewater treatment plant effluent outfall in Canada. This paper discusses contract administration challenges encountered throughout the ABTPO construction phase. Project-specific construction management approaches, issues, and lessons learned are explored, including quality, schedule, risk and claims management, as well as the application of a Dispute Review Board (DRB). Owner and Consultant perspectives discuss how claims were successfully resolved for ABTPO. Contract administration insights for major disputes are presented, including a stuck bucket during shaft secant pile installation, three separate Differing Site Conditions (DSC) events involving unexpected adverse ground conditions with water inflows at greater than 400 lpm during Tunnel Boring Machine (TBM) tunnelling, and off-shore work claims involving riser installation DSC and marine weather conditions (e.g., adverse wind and waves). Lessons learned from successfully resolving these claims are also presented.

Hatch (Canada) (CA), Toronto Public Health (CA), Ministry of Infrastructure (RW)
Openalex Percentile: Top 82%
Law, Economics, and Judicial Systems
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

The Art of Managing Contracts: Insights from the City of Toronto Ashbridges Bay Treatment Plant Outfall — Vlad Petran, Justyna Kempa-Teper, et al. · (2024) | TGRS Research Map | TGRS