Installing Pipeline within Power Right-of-Way: What Could Go Wrong?

The project consists of installing roughly 9-mi of 42-in. pipe. The pipeline alignment is along an existing transmission power corridor, within an easement at an abandoned landfill, and along a public right-of-way adjacent to an active landfill. In addition to the challenges arising from the project being located primarily within coastal wetlands of South Florida, the project had to overcome an aggressive schedule, with design, permitting, and installation needing to be completed within 2 years of notice to proceed. The challenges observed on this project included difficult site conditions, with the contractor having to battle a high groundwater table, unstable soils, and tidal influences, coordination with local and federal stakeholders, installation parallel to an existing 54″ PCCP force main, and high voltage transmission lines. This paper will focus on discussing the various challenges observed and the solutions and strategies implemented to overcome the setbacks.

Authors

Institutions

Publication Details

Published
2024-08-30
DOI
https://doi.org/10.1061/9780784485569.018
Citations
1
Primary Topic
Power System Reliability and Maintenance
Type
article
Field-Weighted Citation Impact
0.36
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Installing Pipeline within Power Right-of-Way: What Could Go Wrong?

Olena Lytvyn
1 citations
Power System Reliability and Maintenance
0.36
article

Installing Pipeline within Power Right-of-Way: What Could Go Wrong?

Olena Lytvyn
article en
1 citations

Abstract

The project consists of installing roughly 9-mi of 42-in. pipe. The pipeline alignment is along an existing transmission power corridor, within an easement at an abandoned landfill, and along a public right-of-way adjacent to an active landfill. In addition to the challenges arising from the project being located primarily within coastal wetlands of South Florida, the project had to overcome an aggressive schedule, with design, permitting, and installation needing to be completed within 2 years of notice to proceed. The challenges observed on this project included difficult site conditions, with the contractor having to battle a high groundwater table, unstable soils, and tidal influences, coordination with local and federal stakeholders, installation parallel to an existing 54″ PCCP force main, and high voltage transmission lines. This paper will focus on discussing the various challenges observed and the solutions and strategies implemented to overcome the setbacks.

Black & Veatch (United Kingdom) (GB)
Openalex Percentile: Top 41%
Power System Reliability and Maintenance
0.36
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.