Optimalisasi Produktivitas Keterlambatan MEP (Mechanichal Elektrikal Plumbing) Gedung F Poliklinik Terpadu RSUD Prof Dr Soekandar Mojosari Kabupaten Mojokerto Melalui Metode Earned Value

This study aims to optimize the productivity of MEP (Mechanical, Electrical, Plumbing) work on the Integrated Polyclinic Building F construction project at Prof. Dr. Soekandar Mojosari Hospital, Mojokerto Regency using the Earned Value (EV) method. The main problems that often occur in construction projects are delays in completion time and cost overruns that can result in decreased productivity. The Earned Value method is used as a management tool to quantitatively measure project performance and provide more accurate information about project progress and deviations from the planned schedule and budget. This research analyzes project performance data through three main variables: Planned Value, Earned Value, and Actual Cost. The analysis showed that there were several errors that caused the project to be delayed and over budget. Using performance indicators such as Schedule Performance Index and Cost Performance Index, this study found important areas that need improvement and recommended optimization strategies to improve the efficiency and effectiveness of MEP works. It is expected that the implementation of these strategies will minimize delays and control costs, so that project objectives can be achieved within the set time and budget.

Authors

Institutions

Publication Details

Journal
Jurnal Basement.
Published
2024-08-23
DOI
https://doi.org/10.36873/basement.v2i2.14831
Primary Topic
Engineering and Technology Innovations
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimalisasi Produktivitas Keterlambatan MEP (Mechanichal Elektrikal Plumbing) Gedung F Poliklinik Terpadu RSUD Prof Dr Soekandar Mojosari Kabupaten Mojokerto Melalui Metode Earned Value

Irawan Irawan, Cilda Thesisa
Jurnal Basement.
Engineering and Technology Innovations
article

Optimalisasi Produktivitas Keterlambatan MEP (Mechanichal Elektrikal Plumbing) Gedung F Poliklinik Terpadu RSUD Prof Dr Soekandar Mojosari Kabupaten Mojokerto Melalui Metode Earned Value

Irawan Irawan, Cilda Thesisa
article en

Abstract

This study aims to optimize the productivity of MEP (Mechanical, Electrical, Plumbing) work on the Integrated Polyclinic Building F construction project at Prof. Dr. Soekandar Mojosari Hospital, Mojokerto Regency using the Earned Value (EV) method. The main problems that often occur in construction projects are delays in completion time and cost overruns that can result in decreased productivity. The Earned Value method is used as a management tool to quantitatively measure project performance and provide more accurate information about project progress and deviations from the planned schedule and budget. This research analyzes project performance data through three main variables: Planned Value, Earned Value, and Actual Cost. The analysis showed that there were several errors that caused the project to be delayed and over budget. Using performance indicators such as Schedule Performance Index and Cost Performance Index, this study found important areas that need improvement and recommended optimization strategies to improve the efficiency and effectiveness of MEP works. It is expected that the implementation of these strategies will minimize delays and control costs, so that project objectives can be achieved within the set time and budget.

Jurnal Basement.Vol. 2(2)
Universitas Sunan Giri (ID)
Decent work and economic growth
Openalex Percentile: Top 89%
Engineering and Technology Innovations
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.