Real-time simulation is an important means of verifying the performance of large-scale photovoltaic (PV) power stations, but it faces a contradiction among accuracy, simulation scale, and hardware resources. To address this issue, a real-time modeling method for large-scale PV stations is proposed in this article. By introducing nested fast and simultaneous solution (NFSS) to construct interface at the unit level and optimize the solution process at the station level, the proposed method can realize high accuracy and good applicability real-time simulation. Meanwhile, a simulation platform based on the field programmable gate array (FPGA) hardware is built to verify its correctness and scalability. Compared with the offline model of the same scale PV station, the maximum relative error is less than 4%. Moreover, the real-time simulation of a 100-units station is realized within 2.5-µs time step.

Authors

Institutions

Publication Details

Journal
IEEE Transactions on Industrial Electronics
Published
2024-08-22
DOI
https://doi.org/10.1109/tie.2024.3440469
Citations
3
Primary Topic
Real-time simulation and control systems
Type
article
Field-Weighted Citation Impact
0.98
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Real-Time Modeling Method for Large-Scale Photovoltaic Power Stations Using Nested Fast and Simultaneous Solution

Shengwei Li, Linhong Guo, Jianzhong Xu, Haiping Guo et al.
3 citations
IEEE Transactions on Industrial Electronics
Real-time simulation and control systems
0.98
article

Real-Time Modeling Method for Large-Scale Photovoltaic Power Stations Using Nested Fast and Simultaneous Solution

Shengwei Li, Linhong Guo, Jianzhong Xu, Haiping Guo, Shiwei Xia
article en
3 citations

Abstract

Real-time simulation is an important means of verifying the performance of large-scale photovoltaic (PV) power stations, but it faces a contradiction among accuracy, simulation scale, and hardware resources. To address this issue, a real-time modeling method for large-scale PV stations is proposed in this article. By introducing nested fast and simultaneous solution (NFSS) to construct interface at the unit level and optimize the solution process at the station level, the proposed method can realize high accuracy and good applicability real-time simulation. Meanwhile, a simulation platform based on the field programmable gate array (FPGA) hardware is built to verify its correctness and scalability. Compared with the offline model of the same scale PV station, the maximum relative error is less than 4%. Moreover, the real-time simulation of a 100-units station is realized within 2.5-µs time step.

IEEE Transactions on Industrial ElectronicsVol. 72(3)
North China Electric Power University (CN), China Southern Power Grid (China) (CN)
Affordable and clean energy
Openalex Percentile: Top 24%
Real-time simulation and control systems
0.98
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.