Exploring Stakeholders’ Perspectives on the Barriers to the Application of Cost-Reduction Techniques in Public Higher Educational Building Delivery

The assessment of barriers to the application of cost-reduction techniques in delivering educational buildings in Nigeria is essential in addressing the infrastructural shortage, building performance, delay, cost, time overrun, and abandonment in the delivery of higher educational buildings (HEBs). This study examines barriers to applying cost-reduction techniques in educational buildings in southwestern Nigeria. Using a survey design, the questionnaire was distributed to stakeholders who participated in delivering the government intervention, private donors, and internally generated revenue educational buildings in public tertiary institutions in southwestern Nigeria from 2012 to 2022. A total of 150 copies of the questionnaire were administered, while 133 responses were obtained and analyzed. To begin with, data reliability and validity were examined using Bartlett’s sphericity, Cronbach’s alpha, and Kaiser–Meyer–Olkin (KMO) tests, accordingly, followed by descriptive, Kruskal–Wallis H test, and exploratory factor analysis. The six components obtained from exploratory factor analysis for explaining the barriers to applying cost-reduction techniques in educational buildings were as follows: ambiguity in HEB contracts awards and project executions, lack of control from the HEIs management over HEB project delivery, perceived political influence in HEB procurement, unrealistic contract requirements and change orders, non-prioritization of automation integration in HEB delivery, and deficiencies in contract documents and costing. This study recommends establishing a project-monitoring team involving independent consultants from project inception to reduce excessive errors, practices of assigning contracts to the lowest bidder, and excessive claims for variation orders that escalate the project’s final sum.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2024-08-19
DOI
https://doi.org/10.3390/buildings14082551
Citations
4
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
1.06

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Exploring Stakeholders’ Perspectives on the Barriers to the Application of Cost-Reduction Techniques in Public Higher Educational Building Delivery

Gbemisola Ajoke Akinola, Olabosipo I. Fagbenle, Ayodeji Ogunde
4 citations
Buildings
BIM and Construction Integration
1.06
article

Exploring Stakeholders’ Perspectives on the Barriers to the Application of Cost-Reduction Techniques in Public Higher Educational Building Delivery

Gbemisola Ajoke Akinola, Olabosipo I. Fagbenle, Ayodeji Ogunde
article en
4 citations

Abstract

The assessment of barriers to the application of cost-reduction techniques in delivering educational buildings in Nigeria is essential in addressing the infrastructural shortage, building performance, delay, cost, time overrun, and abandonment in the delivery of higher educational buildings (HEBs). This study examines barriers to applying cost-reduction techniques in educational buildings in southwestern Nigeria. Using a survey design, the questionnaire was distributed to stakeholders who participated in delivering the government intervention, private donors, and internally generated revenue educational buildings in public tertiary institutions in southwestern Nigeria from 2012 to 2022. A total of 150 copies of the questionnaire were administered, while 133 responses were obtained and analyzed. To begin with, data reliability and validity were examined using Bartlett’s sphericity, Cronbach’s alpha, and Kaiser–Meyer–Olkin (KMO) tests, accordingly, followed by descriptive, Kruskal–Wallis H test, and exploratory factor analysis. The six components obtained from exploratory factor analysis for explaining the barriers to applying cost-reduction techniques in educational buildings were as follows: ambiguity in HEB contracts awards and project executions, lack of control from the HEIs management over HEB project delivery, perceived political influence in HEB procurement, unrealistic contract requirements and change orders, non-prioritization of automation integration in HEB delivery, and deficiencies in contract documents and costing. This study recommends establishing a project-monitoring team involving independent consultants from project inception to reduce excessive errors, practices of assigning contracts to the lowest bidder, and excessive claims for variation orders that escalate the project’s final sum.

BuildingsVol. 14(8)
Covenant University (NG), The Federal Polytechnic, Ado-Ekiti (NG), The Federal Polytechnic Ilaro
Covenant University, Covenant University Centre for Research, Innovation and Discovery
Openalex Percentile: Top 25%
BIM and Construction Integration
1.06
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.