EFFECT OF TIME ELAPSED BETWEEN SUCCESSIVE CONCRETE POURINGS AND LOCATION OF THE COLD JOINTS ON THE FLEXURAL CAPACITY OF RC BEAMS

This research investigates the effect of the time interval between successive concrete pouring and the position of cold joints on properties and bending strength capacity in reinforced beams. Two horizontal cold joints were examined: another positioned in the zone of compressions (h=110 mm) and one situated in the beam's tension area ( h = 50mm). In both cold joint elevations, the time interval between two mert patches was varied as 1.5 hrs.,3 hr and 4 hrs. Furthermore, six nominally standardized RC beams were tested and analyzed with a reference beam devoid of cold joints. The obtained outcomes revealed the decrease of beams' ultimate flexural capacity with an increase in time elapsed between periods of pouring from 1.5 to 4.5 hours. The reduction in flexural strength was more evident when a cold joint went through the compression fibre of a beam. Additionally, the hardness and rigidity of the tested beams roughly inversely correlated with time intervals between consecutive pourings. More specifically, the percentage reduction in ultimate load, stiffness and toughness of cold joints for tension fibres at 1.5 hours was (4.36% ,9.7% and 9.3%) while that of compression fibre was (5.36%),(34.2%)and ( 34.5% ) % respectively when compared with control beam.

Authors

Institutions

Publication Details

Journal
Jurnal Teknologi
Published
2024-08-12
DOI
https://doi.org/10.11113/jurnalteknologi.v86.21966
Primary Topic
Structural Behavior of Reinforced Concrete
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

EFFECT OF TIME ELAPSED BETWEEN SUCCESSIVE CONCRETE POURINGS AND LOCATION OF THE COLD JOINTS ON THE FLEXURAL CAPACITY OF RC BEAMS

Ali Abd Sultan, Maysaa Aziz Mahdi
Jurnal Teknologi
Structural Behavior of Reinforced Concrete
article

EFFECT OF TIME ELAPSED BETWEEN SUCCESSIVE CONCRETE POURINGS AND LOCATION OF THE COLD JOINTS ON THE FLEXURAL CAPACITY OF RC BEAMS

Ali Abd Sultan, Maysaa Aziz Mahdi
article en

Abstract

This research investigates the effect of the time interval between successive concrete pouring and the position of cold joints on properties and bending strength capacity in reinforced beams. Two horizontal cold joints were examined: another positioned in the zone of compressions (h=110 mm) and one situated in the beam's tension area ( h = 50mm). In both cold joint elevations, the time interval between two mert patches was varied as 1.5 hrs.,3 hr and 4 hrs. Furthermore, six nominally standardized RC beams were tested and analyzed with a reference beam devoid of cold joints. The obtained outcomes revealed the decrease of beams' ultimate flexural capacity with an increase in time elapsed between periods of pouring from 1.5 to 4.5 hours. The reduction in flexural strength was more evident when a cold joint went through the compression fibre of a beam. Additionally, the hardness and rigidity of the tested beams roughly inversely correlated with time intervals between consecutive pourings. More specifically, the percentage reduction in ultimate load, stiffness and toughness of cold joints for tension fibres at 1.5 hours was (4.36% ,9.7% and 9.3%) while that of compression fibre was (5.36%),(34.2%)and ( 34.5% ) % respectively when compared with control beam.

Jurnal TeknologiVol. 86(5)
Thi Qar University (IQ)
Sustainable cities and communities
Openalex Percentile: Top 87%
Structural Behavior of Reinforced Concrete
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.