Variations and Claims in International Construction Projects in the MENA Region from the Last Decade

This study delves into the dynamics of ‘Variations’ and ‘Claims’ in construction projects. This study aims to identify, categorize, and devise mitigation strategies for critical types of variations and claims that are aligned with the contract’s FIDIC conditions. The research draws on input from construction industry professionals, including contract administrators and project managers, and focuses on the MENA region. The region’s extensive adoption of FIDIC standards and the rapidly growing construction sector drive this choice. Data collection encompassed a questionnaire distributed to 80 industry experts, predominantly through interviews focused on countries such as Saudi Arabia, the UAE, Kuwait, and Egypt. Utilizing SPSS-V.25 for statistical analysis, this study uncovers the most prevalent and impactful causes of variations and claims, highlighting the critical need for managerial intervention. A key feature is the integration of scientometric analysis into a quantitative finding. Implementing a k-means clustering analysis is a significant addition to the methodology. The survey had high internal consistency with a Cronbach’s alpha of 0.97, and the respondents reported frequent and significant claims such as delayed drawings, ambiguous documents, and client changes. The results showed that effective claims management requires clear communication and balanced contracts, while poor design and contract documentation cause variations and claims. The correlation analysis showed strong positive correlations between claim types and causes. To reduce claims and address these factors, most respondents said the survey could predict and reduce claims.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2024-08-13
DOI
https://doi.org/10.3390/buildings14082496
Citations
6
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.94
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Variations and Claims in International Construction Projects in the MENA Region from the Last Decade

Ruqaya Al-Sabah, Ahmed Mohammed Abdelalim, Mohamed Tantawy, Salah Omar Said et al.
6 citations
Buildings
Construction Project Management and Performance
2.94
article

Variations and Claims in International Construction Projects in the MENA Region from the Last Decade

Ruqaya Al-Sabah, Ahmed Mohammed Abdelalim, Mohamed Tantawy, Salah Omar Said, Mohamed Salem, Mohamed Ramadan Ezz Al-Regal
article en
6 citations

Abstract

This study delves into the dynamics of ‘Variations’ and ‘Claims’ in construction projects. This study aims to identify, categorize, and devise mitigation strategies for critical types of variations and claims that are aligned with the contract’s FIDIC conditions. The research draws on input from construction industry professionals, including contract administrators and project managers, and focuses on the MENA region. The region’s extensive adoption of FIDIC standards and the rapidly growing construction sector drive this choice. Data collection encompassed a questionnaire distributed to 80 industry experts, predominantly through interviews focused on countries such as Saudi Arabia, the UAE, Kuwait, and Egypt. Utilizing SPSS-V.25 for statistical analysis, this study uncovers the most prevalent and impactful causes of variations and claims, highlighting the critical need for managerial intervention. A key feature is the integration of scientometric analysis into a quantitative finding. Implementing a k-means clustering analysis is a significant addition to the methodology. The survey had high internal consistency with a Cronbach’s alpha of 0.97, and the respondents reported frequent and significant claims such as delayed drawings, ambiguous documents, and client changes. The results showed that effective claims management requires clear communication and balanced contracts, while poor design and contract documentation cause variations and claims. The correlation analysis showed strong positive correlations between claim types and causes. To reduce claims and address these factors, most respondents said the survey could predict and reduce claims.

BuildingsVol. 14(8)
Kuwait Petroleum Corporation (Kuwait) (KW), Kuwait University (KW), Australian University, Kuwait (KW), Helwan University (EG)
Partnerships for the goals
Openalex Percentile: Top 9%
Construction Project Management and Performance
2.94
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.